上海浦东国际机场第四跑道项目
飞行区场道及附属设施工程(四标段)
安防管道施工方案
施工单位:中交一航局第四工程有限公司第十项目部
编 制: 赵 义 财 审 核: 闫 国 龙 批 准: 张 绍 栋 日 期: 2012年02月18日
目 录
一、编制原则 ............................................................................................................... 1 二、工程概述 ............................................................................................................... 4 三、施工技术要求 ..................................................................................................... 5 1、给水回水管线 ································································································ 3 2、安防供电、通讯管线 ....................................................................................... 5 四、施工准备 ............................................................................................................... 6 1、技术准备 ....................................................................................... 6 2、材料准备 ........................................................................................ 6 3、机具准备 ........................................................................................ 7 五、施工方案 ............................................................................................................... 7 1.1、管线施工工艺................................................................................................. 7 1.1.1、 管道工程工艺流程 ................................................................................. 7 1.1.2、测量放样 .................................................................................. 7 1.1.3、 管沟开挖 .................................................................................................... 9 1.1.5、 管节安装 .................................................................................................. 11 1.1.6、 管道敷设 .................................................................................................. 12 1.1.7、沟槽回填 ···································································································· 11 1.1.8、管道回填 ................................................................. 错误!未定义书签。 1.2、安防手井施工工艺 ..................................................................................... 14 1.2.1、安防手井施工流程 ................................................................................ 14
1.2.2测量定位 ....................................................................................................... 15 1.2.3、基槽开挖 ................................................................................................... 15 1.2.4、碎石垫层 ................................................................................................... 15 1.2.5、素砼垫层 ................................................................................................... 15 1.2.6、钢筋绑扎 ................................................................................................... 15 1.2.7、模板支撑 ................................................................................................... 16 1.2.8、砼浇筑 ........................................................................................................ 17 1.2.9、拆模、养生............................................................................................... 18 六、施工进度计划 .................................................................................................... 19 七、工程质量保证措施及检测内容 ................................................................. 19
上海浦东国际机场第四跑道项目 飞行区场道及附属设施工程(四标段)
安防管线预埋方案
一、编制原则
1、上海虹桥国际机场扩建工程飞行区场道及附属设施工程设计说明和施工图纸;
2、《民用机场飞行区工程竣工验收质量检验评定标准》(MH5007-2000)
3、中国民用航空总局《民航机场飞行区技术标准》(MH5001-2006) 4、国家及民航其他有关的标准、规范和规定。 5、我单位现场踏勘,自然状况调查咨询资料。 二、工程概述
本工程位置处于跑道南侧,安防管道预埋管道预埋及基础工程包括安防供电预埋管、镀锌钢管、高强度栅格通信管、塑合金复合通信管等,其管内预留二根8#镀锌铁丝作为牵引线,沟槽开挖、敷设、混凝土包封等。监控摄像机的立杆/中杆、以及立杆/中杆的脚踏固定件、举行钢固定件、环形箍、避雷针及其托背、底板等基础制作安装,包括土方开挖、预埋地脚螺栓、预埋钢管、接入管等。基础还包括各类人井、手井的施工。
名称 4*4栅格管 1*4栅格管 8*4栅格管 10*4栅格管 塑合金管 钢管管道DN150 管道混凝土包封8*4栅格管 安防手孔井 安防接线井 安防人孔井 控制箱(交接箱)基础 单位 m m m m m m m 个 个 个 个 工程量 1834 322 961 285 250 176 120 27 27 13 1 备注 三、施工技术要求 1、安防通讯管线
1.1、混凝土基础和包封采用C15商品混凝土浇注,手井井体采用C30商品混凝土浇注。
细土回填压实度达到0.87。
1.2安防管线接口处采用塑合金复合套管,管与管接口处两侧的套管长度不小于30cm,拐弯处采用特制弯头。弯头的弯折度要适宜,确保管子的韧性不被破坏。
控制措施及注意事项:
①管管相接时必须要严密,管端必须清洁,管道安装时清扫管道中的杂物;临时停止施工时,管端应封堵。
②套管完毕后,必须要牢固,以免混凝土包封时碰动套管,漏缝。