一、编制说明 ........................................................................................................................................................................... 0 1.1编制目的 ......................................................................................................................................................................... 0 1.2适用时间与范围 ............................................................................................................................................................. 0 1.3编制依据 ......................................................................................................................................................................... 0 1.4编制原则 ......................................................................................................................................................................... 0 二、工程概况 ........................................................................................................................................................................... 1 1.1 总体简介 ........................................................................................................................................................................ 1 1.2 气候条件 ........................................................................................................................................................................ 1 三 施工部署 ............................................................................................................................................................................. 1 3.1 冬施时间 ........................................................................................................................................................................ 1 3.2 冬施部位 ........................................................................................................................................................................ 2 3.3组织机构 ......................................................................................................................................................................... 2 3.4前期准备 ......................................................................................................................................................................... 2 四 施工准备 ............................................................................................................................................................................. 2 4.1组织准备 ......................................................................................................................................................................... 2 4.2技术准备 ......................................................................................................................................................................... 3 4.3现场准备 ......................................................................................................................................................................... 4 4.4物资准备 ......................................................................................................................................................................... 5 4.5安全与防火 ..................................................................................................................................................................... 5 五 冬期施工技术措施 ............................................................................................................................................................. 6 5.1临时管线、管沟管理 ..................................................................................................................................................... 6 5.2水暖、管道工程 ............................................................................................................................................................. 6 5.3生活安排 ......................................................................................................................................................................... 6 5.4钢筋工程 ....................................................................................................................................... 错误!未定义书签。 5.5混凝土工程 ..................................................................................................................................................................... 6 5.6混凝土蓄热法养护及热工计算 ................................................................................................................................... 10 5.7砌体工程 ....................................................................................................................................................................... 16 5.8回填土施工 .................................................................................................................................. 错误!未定义书签。 六.混凝土质量检查 ............................................................................................................................................................... 19 七 越冬工程维护 ................................................................................................................................................................... 20 7.1基本要求 ....................................................................................................................................................................... 20 7.2在建工程 ....................................................................................................................................................................... 20 7.3冬期停建工程 ............................................................................................................................................................... 20 八 质量保证措施 ................................................................................................................................................................... 21 九 消防安全措施 ................................................................................................................................................................... 21
一、编制说明
1.1编制目的
根据《铁路混凝土工程施工质量验收标准》(TB10424-2010)规定:根据当地多年气象资料统计,当工地昼夜平均气温连续3d低于+5℃或最低气温低于-3℃时,应采取冬期施工措施;当工地昼夜平均气温高于5℃时,应解除冬期施工。
为了保证工程施工不因冬季温度影响施工质量、耽误工期,并加强冬季施工的综合管理,特编制此方案。
1.2适用时间与范围
方案适用范围为本标段工程的施工,适用时间为毕节地区的冬季( 11月~ 次年2月),需要在施工进入冬季之前制定相应的冬季施工措施。
1.3编制依据
1《建筑工程施工质量验收统一标准》(GB50300-2001) 2《混凝土结构工程施工质量验收规范》(GB50204-2002) 3《砌体工程施工质量验收规范》(GB50203-2002) 4《建筑装饰装修工程施工质量验收规范》(GB50210-2001) 5《建筑地基基础工程施工质量验收规范》(GB50202-2002) 6《混凝土外加剂应用技术规程》(GB50119-2003) 7《混凝土强度检验评定标准》(GB/T50107-2010) 8《建筑工程冬期施工规程》(JGJ 104-97); 9 本标段施工图设计文件及部分招标设计文件; 10《钢筋焊接及验收规程》(JGJ18—1996); 11《简明施工计算手册》(第三版);
12工程现场实际情况以及我单位施工经验、施工技术与管理水平以及多年来相关工程实践中积累的施工及管理经验,并学习了地铁参建兄弟单位的冬施经验。
1.4编制原则
通过充分研究工程内容和现场施工环境,严格执行相关标准、规范和规程,并采用技术先进、方案可靠、经济合理的技术措施,确保实现业主要求的工期、质量、安全、环境保护、文明施工
和职业健康等各方面的工程目标。
二、工程概况
1.1 总体简介
序 号 1 2 3 4 5 6 7 8 9
项 目 工程名称 工程地址 建设单位 设计单位 监理公司 质量监督 施工单位 总建筑面积 结构形式 内 容 新建织金至毕节铁路站后“四电”集成及相关工程 新建织金至毕节铁路毕节东站 成都铁路局贵阳建设指挥部 中国中铁二院工程集团有限责任公司 成都大西南铁路监理有限公司 成都铁路局贵阳质量监督站 中铁十一、十二局集团联合体织毕铁路站后工程指挥部 28700㎡ 框架结构、砖混结构、砌体结构 1.2 气候条件
本地区属暖温带大陆性半半湿润季风气候区。其特点是:四季分明,雨热同季、干冷同期、温度适宜、光照充裕。年平均气温为9.3℃,最冷的1月份平均气温为-8.8℃,最热的7月份平均气温为24.7℃,极端最冷气温为20.5℃,极端最热气温为39℃.年平均降水量为30.5毫米。年日照时数2725.9小时,年蒸发量为1829.3毫米。全年平均风速为3.3米/秒,最大风速可达25.3米/秒.终霜日为2月16日,初霜日为10月5日。7、8 月份为雨期,冬期施工日期本年11 月15 日至次年2月25 日。
三 施工部署
3.1 冬施时间
根据《建筑工程冬期施工规程》JGJ104-97规定:
冬期来临时的判定,当连续5天的日平均气温稳定低于5℃,或日最低气温低于0℃时,则此5日后的第一日为进入冬施的初日;当天气转暖,连续5天的日平均气温稳定高于5℃,最后一个5天的日平均气温稳定在5℃以上时,则此5天后的第一天为冬施的终止日。根据常年气温资料,毕节地区地区冬施期间为11月15日起,来年2月25日止,约100天。
3.2 冬施部位
根据工程进度计划安排,冬季施工的主要内容:混凝土工程、砌体工程、管道工程,基于上述的施工内容,冬季施工将以以下项目为主要控制目标,确保施工质量:
(1)混凝土工程; (2)砌体工程; (3)管道工程。
3.3组织机构
项目成立冬季施工领导小组,主管工程冬期施工的准备、实行、落实、检查等工作,具体人员组成及分工如下表:
姓名 王彦生 职务 责 任 项目经理,组长 全面负责项目的冬期施工领导工作 王万云 技术负责,副组长 冬季施工方案、措施的制订与编制,技术问题的处理 尚海涛 陈效贤 曹 阳 朱柳诚 朱文军 朱友良 安全员 质检员 材料员 砼工长 机电工长 试验员 负责冬期施工期间的安全、消防、防火及现场的文明施工 全面检查冬施期间各分部分项工程的质量情况 负责冬期施工物资的采购、保管 管理施工现场冬施措施的具体实施情况: 混凝土浇筑后的保温养护工作;墙、板的保温工作检查; 负责现场临时水电线路的冬期保温措施的落实、检查与维修 负责每日测温以及施工中的取样送检工作
3.4前期准备
在11月15日前根据施工方案准备冬施材料、仪器的采购,与商混站联系进行混凝土外加剂准备及交底。对现场相关管理人员及施工作业人员进行技术、安全交底。
四 施工准备
4.1组织准备
4.1.1进行冬期施工的工程项目,在入冬前应组织专人编制冬期施工方案。编制的原则是:确保
工程质量;经济合理,使增加的费用为最少;所需的热源和材料有可靠的来源,并尽量减少
能源消耗;确实能缩短工期。冬期施工方案应包括以下内容:施工程序;施工方法;现场布置;设备、材料、能源、工具的供应计划;安全防火措施;测温制度和质量检查制度等。方案确定后,要组织有关人员学习,并向班组进行交底。
4.1.2进入冬期施工前,对掺外加剂人员、测温保温人员、锅炉司炉工和火炉管理人员,应专门
组织技术业务培训,学习本工作范围内的有关知识,明确职责,经考试合格后,方准上岗工作。
4.1.3与当地气象台站保持联系,及时接收天气预报,防止寒流突然袭击。
4.1.4安排专人测量施工期间的室外气温,暖棚内气温,砂浆、混凝土的温度并做好记录。 4.1.5冬期施工的各项措施主要以预防为主。对进入冬期施工的工程项目、部位、工程量等进行
核实,对所需的劳动力、资源、机械设备、冬期施工流向作出统筹安排。
4.1.6在施工现场设立天气预报黑板,前一天写明第二天气象台的天气预报情况;每天2:00、8:
00、14:00、20:00将当时大气温度实测值和平均值填入黑板,同时及时填报冬施混凝土入模温度统计表。设立四个测温标识牌,挂在相应测温部位上,测温的同时把记录填上。
4.2技术准备
冬施前认真查阅施工图纸、方案、相关安全质量规范,找出冬施中要进行的分项工程及所用的人、机、料、施工工艺、安全质量施工注意点等,作到冬施中重点突出、心中有数。组织管理人员学习《冬期施工规程》、进行冬施方案交底,提高冬施安全、质量、技术等意识,避免在冬施中造成损失。对工人的冬施技术交底,培训测温人员,提高对冬施工作的责任心和操作水平(保证测温记录的真实性、完整、准确性,经常每日早晚拨打122与气象部门电话联系等)。 4.2.1认真学习贯彻国家有关冬期施工的规范、规程及公司的有关文件,组织所有参加冬施的人
员进行冬施培训。
4.2.2冬施前应仔细复核图纸,对于结构保温性能较薄弱的部位应重点加强其保温措施。 4.2.3根据规范要求贵州省毕节市冬天的气温情况,本工程冬施采用“综合蓄热法”施工。混凝
土采用商品混凝土,墙体保温为外表面粘贴聚苯板;站场硬化面和房屋楼板浇筑混凝土后表面铺塑料布再覆盖土工布;楼板下根据温度变化情况,准备火炉,随时加热保温。 4.2.4冬期施工培训:冬期施工前由技术负责人组织向施工管理人员、技术骨干、工长及班组长
作冬施方案交底和培训,明确施工方案、技术措施、施工方法、质量要求、施工试验要求。工长应进行详细技术交底,使所有操作人员都明确冬施期间的具体要求。