好文档 - 专业文书写作范文服务资料分享网站

【施工方案】大坝填筑施工方案

天下 分享 时间: 加入收藏 我要投稿 点赞

目 录

1。 概述 ·············································································· 1

1.1。 工程概况 ································································· 1 1.2。 编制依据 ································································· 2 1。3. 坝体填筑料主要工程量及技术要求 ································ 2 2。 施工布置 ········································································ 4

2.1。 施工道路的布置 ························································ 4 2.2。 施工用水、电布置 ····················································· 5 2.3。 主坝上游基坑排水布置 ··············································· 5 3。 坝体填筑施工 ·································································· 6

3。1。 坝体填筑原则 ························································· 6 3.2. 大坝填筑施工工艺及坝面划分原则·································· 8 3。3. 坝料开采加工与平衡 ·················································· 9 3。4。 坝料运输 ···························································· 12 3。5。 基础面清理及验收 ················································ 13 3.6。 过渡(反滤料)填筑 ················································· 13 3.7。 全强风化料填筑 ····················································· 14 3。8。 排水料填筑 ························································· 16 3。9. 特殊部位结合面处理 ··············································· 16 3.10. 干砌石护坡的施工 ·················································· 18 3.11. 沥青心墙施工 ························································ 19 4。 雨季施工 ····································································· 19

4.1。 雨季施工措施 ························································ 19 4.2。 其它控制措施 ························································ 20 4。3。 雨期坝面排水措施 ················································ 21 5. 施工安全及质量保证措施 ··················································· 21

5。1。 安全保证措施 ······················································ 21 5。2. 施工准备阶段质量保证措施 ······································ 22 5。3. 坝体填筑过程质量保证措施 ······································ 24 5.4。 总体质量保证措施 ·················································· 26 5.5. 各类坝料填筑检查项目及取样次数、控制标准和碾压机械技术性能 ················································································ 28 5.6. 坝体质量控制关键点 ················································ 28 6。 施工进度计划及工期保证措施 ·········································· 30

6.1. 施工进度计划 ························································· 30 6.2. 施工强度分析 ························································· 30 6。3。 工期保证措施 ······················································ 32 7。 资源配置 ····································································· 33

7。1。 管理人员配置 ······················································ 33 7.2. 劳动力安排 ···························································· 34 7。3. 施工机械设备的配置 ··············································· 34 8. 安全文明生产及环境保护措施 ············································· 35

8。1. 料场 ···································································· 35 8。2。 坝料运输 ···························································· 35 8。3. 坝料填筑 ······························································ 37 9。 强制性条文 ·································································· 37

1.概述

1.1.工程概况

水库地处,主要建筑物有主坝和溢洪道。主、副坝均采用沥青混凝土心墙土石坝,主坝顶高程m,最大坝高30。0m;主坝右岸设自溢竖井式溢洪道,结合导流洞改造而成.上水库正常蓄水位m,死水位m,调节库容m3,死库容万m3,总库容m3。

坝顶宽度8.0m.坝顶上游设防浪墙,下游设L型挡墙。大坝上游坝坡为1:30;下游坝坡为1:2.7,高程555.00m处设一马道,马道宽度为4m.沥青混凝土心墙位于大坝上游侧,心墙中心桩号坝0+002.200m,为厚0.5m的等厚心墙。当沥青混凝土心墙部位坝基全风化层厚度大于5m时,采用混凝土防渗墙连接;对于主坝右岸全强风化较薄部位,采用混凝土基座连接,基础开挖至弱风化基岩.沥青混凝土心墙采用底部端头加厚平接方式,接触面设沥青马蹄脂及一道铜止水。

坝体填筑料分区从上游至下游依次为:干砌块石护坡、碎石垫层、上游全强风化料区、上游过渡区、沥青混凝土心墙、下游过渡区、下游全强风化料区和下游坝面草皮护坡,心墙上下游过渡层水平宽度均为2。0m。另外下游坝基清坡后设0。5m厚的中砂反滤层,反滤层与全强风化料间设2。0m厚碎石层,作为下游坝体排水体。

上游护坡区:上游边坡设一级坡,坡比为1∶3.0,采用干砌块石护坡.干砌块石层厚0.5m,石料粒径30cm~50cm;其底部为级配碎石垫层兼反滤层,厚度0.5m,石料粒径为0.5cm~8cm。护坡所需石料均从石料场取料,为新鲜花岗岩,其中碎石料由人工扎制而成。

1.2.编制依据

⑴ 、坝体填筑要求:《沥青混凝土心墙土石坝填筑施工技术要求》; ⑵ 、设计图纸;

⑶ 、《土建工程施工技术条款》;

⑷ 、《碾压式土石坝施工规范》(DL/T5129—2001)。 ⑸ 、《水工碾压式沥青混凝土施工规范》(DL/T5363—2006)。 1.3.坝体填筑料主要工程量及技术要求 1、坝体填筑主要工程量见下表

坝体填筑主要工程量

序号 1 2 部位 坝料名称 沥青混凝土 坝体全强风化料 单位 m3 m3 方量 备注 厚50cm 中粒径花岗岩全、强风化料,块石最大粒径小于300mm 沥青混凝土心墙两侧过渡3 过渡料级配碎石料 m3 料、粒径小于80mm的级配碎石 上水库 4 下游坝基垫层料级配m3 碎石料 5 级配中砂反滤料 上游坝坡垫层料级配m3 6 碎石料 7 上游坝坡干砌石 m3 m3 下游坝基排水垫层料、粒径小于40mm的级配 碎石 下游坝基反滤层、粒径小于5mm的级配中砂 上游坝坡护坡垫层料、粒径为5~80mm的级配 碎石 石料粒径均值30cm~50cm新鲜花岗岩 2、填坝料施工质量控制要求

1)、上、下游全强风化料区:全强风化料采用上水库进出水口、溢洪道、库岸防护、备用料场等建筑物开挖土石料。全风化料碾压后强度指标要求干容重不小于1.68t/m3,强风化料碾压后强度指标要求干容重不小于1。

91t/m3。设计上、下游全强风化区填筑料级配见下表

强风化花岗岩填筑料级配表

粒径范围(mm) 占总重百分比(%) 300~200 20 200~100 26 100~80~60~40~20~10~5 <5 <0.075 80 60 40 20 10 7 7 8 10 7 5 10 1 粒径小于5mm全风化花岗岩填筑料级配表

粒径范围(mm) 占总重百分比(%) 5~2 34 2~0.5 26。2 0。5~0.25 4。9 0。25~0。075 5.9 0.075~0。005 〈0.005 11 18 2)、过渡料:为沥青混凝土心墙两边提供均匀支撑,满足心墙与坝壳料之间变形的过渡要求,且具有良好的排水性和渗透稳定性,满足施工要求的承载力。过渡料由新鲜花岗岩人工扎制而成,最大粒径为80mm,小于5mm粒径含量为25%~40%,小于0。075mm粒径含量不超过5%,级配连续,碾压后强度指标要求干容重不小于2.15t/m3。设计过渡料级配见下表

过渡料级配表

粒径范围(mm) 上包线 占总重百分比(%) 平均线 下包线 80~60 60~40 4 11 18 10 12 14 40~20 16 17 18 20~10 15 15 15 10~5 15 12.5 10 <5 40 32.5 25 <0。075 5 3 1 3)、中砂反滤层

坝基清理后,在坝基与排水体之间设0.5m厚的中砂反滤层。碾压后要求干容重2.21 t/m3.设计中砂反滤层级配见下表

中砂级配表

粒径范围(mm) 占总重百分比(%) 〉5 2。9 5~2.5 18。9 2.5~1。25 15。1 1。25~0。0。315~0。0.63~0.315 63 16 22。2 17.9 8。3 <0。16 14。6

4)、排水碎石

采用扎制的人工碎石料,为弱风化~新鲜石料,最大粒径为40mm。碾压后要求干容重2.18t/m3。设计排水碎石典型级配见表.

排水碎石级配表

粒径范围(mm) 占总重百分比(%) 40~30 25 30~20 20 20~10 30 10~5 25 5)、护坡干砌块石及碎石垫层

上游护坡区干砌块石层厚0。5m,石料粒径均值30cm~50cm,其底部为级配碎石垫层兼反滤层,厚度0。5m,石料粒径为0。5cm~8cm.护坡所需石料均从开挖可利用料及石料场取料,为新鲜花岗岩,其中碎石料由人工扎制而成。

2.施工布置

2.1.施工道路的布置

坝体填筑道路根据现场实际情况,综合现有施工道路及地形条件,设3条临时施工道路.分为坝前(4条)上坝道路和坝后(2条)上坝道路及主坝右侧上下游连通道路.坝前、坝后道路主要满足大坝心墙两侧的过渡料、全强风化料、反滤料、排水料、坝前抛石护坡填筑及围堰心墙两侧的过渡料填筑。具体道路见《坝体填筑道路及排水平面布置图》。

随着坝体的上升,在坝坡或坝体内部设置“之”字行上坝道路,以便最大限度的减少坝体外的上坝道路。

上游L1道路为上游主要运输道路,跟随坝体填筑同步上升,L4、L5、L6待坝体填筑至相应终点高程后作为交通道路运输填筑材料,坝体右侧连接道路高程为▽570,▽566坝体填筑主要依靠右侧连通道路运输上坝材料。

下游L3、L2道路跟随坝体填筑同时上升,后期主要依靠L2道路满足上坝填筑的主要运输道路。

2.2.施工用水、电布置 (1)、生产用水

施工供水从左坝头高位水池接水管至各工作面. (2)、施工供电及照明

施工供电从1#变电站接配电柜至各工作面,施工用电主要为照明用电,左右岸各布置一个灯塔,每个灯塔装设2~3个1000W可自由调整照射范围的投灯光。并在上下游各设置2盏可移动的投光灯,保证夜间填筑施工具备足够的照明条件.

2.3.主坝上游基坑排水布置

2016年主坝度汛由其上游围堰承担,围堰不可避免的渗水,基坑内的施工废水,以及雨天基坑的积水需要排出上游围堰。因而,基坑内的排水系统是不可缺少的,也是主坝能否安全正常施工的条件之一。 1 2.3。1 排水系统布置

1 沿上游围堰的下游坡脚设置碎石排水带或排水沟,以汇集围堰渗水。截水沟到上游河床深槽折向主坝上游坝脚前挖填结合形成的集水池,安装排水泵和排水管,向上游围堰外排水,形成主坝上游基坑排水泵站(坝体填筑道路及排水平面布置图)。

1 坝体上游混凝土基座上设置排水碎石带,保证坝体本身渗水的顺利流出,再由两侧的排水体汇集至上游侧的集水坑内抽排。下游的坝体则通过排水碎石层把雨水及地下渗水统一排至下游坝面以外的排水沟里。

1 2。3.2基坑排水

1 基坑内的雨水和废水,以排水沟的形式向上游基坑排水泵站汇集。泵站的容量应以满足渗水、雨水和废水排除的需要。但汛期来临之前,除对机组检修外,还应根据天气、水情增加泵站排水机组和相应排水管道,以及相应的防汛器材,以备防汛之需。 2。3。3左右两岸边坡雨水迳流的控制

左右两岸在坝体上下游坝脚范围内的边坡交接处形成的雨水迳流会冲进基坑内,需要采取一些控制措施,防止雨水冲进心墙区、反滤料区和过渡料区,在两侧边坡马道、台阶及边坡与坝基交接处设置排水沟,将迳流引向坝外,以避免主汛期边坡迳流进入基坑. 1 2.3。4泵站撤除

1 随着坝体填筑的上升,上游坝坡的干砌石护坡应该紧随其后上升.到2016年汛后,或岸坡道路全部撤出基坑,或坝上游砌石高出围堰堰顶时,基坑泵站完成使命,可以撤除,退出基坑.

3.坝体填筑施工

3.1.坝体填筑原则

大坝填筑遵循均衡平起的原则进行,坝体填筑,总体上遵循与沥青混凝土心墙碾压全断面平起均衡上升的施工方法。对坝壳料,根据坝面面积大小及各类坝料分序、分区的不同,将坝面沿坝轴线方向按50~100m分成若干个单元。在各单元依次完成填筑的各道工序,使各单元上所有工序能够连续流水作业。各单元之间进行鲜明标识,标明摊铺、碾压、检验等工作状态,以避免超压或漏压。采用进占法、后退法或两者结合的方式进行卸

料、平整及碾压施工.

大坝填筑时先进行沥青心墙及过渡料的施工,然后进行两侧排水碎石及坝壳料的填筑,总体上沥青心墙要略高于两侧坝壳料的上升,上游面▽557以上开始铺设干砌石护坡,干砌石护坡施工低于坝壳料2~5m,使得块石能够有运输通道.上下游各由1台22t的振动碾、推土机及挖掘机进行配合摊铺碾压.

各种填坝材料的铺填厚度及碾压遍数见生产性实验报告。

3.2.大坝填筑施工工艺及坝面划分原则

3.2.1.大坝填筑标准断面图

上水库坝体填筑典型分区示意图

3.2.2.大坝填筑施工工艺流程图

基础面清理与验收 测量放样各类坝料分界线 心墙线 沥青混凝土心墙及过渡料施工 N 坝料开采、运输、卸料、摊铺、 各类坝料中超径石处理及界面分离料处理 坝料碾压 N 坑检取样

3.2.3.大坝填筑作业面划分原则

1、划分填筑单元的目的

为了使大坝填筑各个工序尽量连续施工,需在填筑作业时划分成若干个工作面或作业单元,以提高坝面上各类施工机械的使用效率,提高上坝

强度。

2、工作面填筑单元划分

每个单元面积的大小,依施工设备的品种、型号和数量而定。单元太小,会给车辆卸料、洒水及碾压造成困难;单元太大,单元数则减少,会给单元的循环造成困难.

(1)上库主坝沥青混凝土心墙最大长度在338m以内,心墙区面积更小,根据类似工程经验,心墙区按照每一层划分为一个单元,划分作业单元后形成进料摊铺、碾压、质量验收流水循环施工作业。

(2)根据填筑规划,全强风化料每个单元面积约4000~10000m2,以平行坝轴线划分条带填筑作业大区,各作业大区可以根据实际情况划分填筑单元。

(3)反滤料各条带填筑区作为一个作业大区组织施工. 3、 填筑单元的循环

作业面划分后,形成作业区流水循环、区内单元流水循环、单元内工序流水循环施工。单元循环的原则是:第一个单元铺料平料,第二个单元洒水碾压,第三个单元质量检查验收,以此循环往复,形成流水作业。

3.3.坝料开采加工与平衡

3.3.1.料场概况

本工程3#料场为本工程开挖利用料,堆存于坝前左岸,利用料约18万m3。4#料场为本工程拌合楼后山体全风化料,利用料约20万m3。5#料场为库心岛全强风化料。利用料约40万m3,过渡料、排水料及反滤料来自下库砂石料加工场。2#料场由于开挖料混存,级配不良后期如果需采用此料

场的土料,由四方根据现场实际情况进行商定取料检测及上坝.3#、5#料场开挖取料至▽555,4#料场开采至▽570。

3.3.2.料场复查

根据对3#、4#、5#料场的复勘核查,3#料场距离坝址直线距离约3km,多为全强风化料的混料,最优含水率为13.6,最大干密度为1。75。4#、5#料场多为较均匀的全风化土料,最优含水率分别为13。8、13.7,最大干密度分别为1。73、1。79。

3.3.3.料场规划

料场使用原则:雨天使用原状料、晴天使用堆存料,坝后采用3#料场的土料,坝前采用5#场的土料,下雨天则采用4#料场的土料。

1、料场剥离:根据料场地势平缓,面积较大的特点并结合上坝工期及强度安排综合考虑。3#料场面层清除杂物及大块石,1.6 m3反铲装车20t自卸车配合拉运至填筑面;4#、5#料场顶部覆盖层采用一次性剥离,剥离的覆盖层可用于开采施工道路的修筑,1。6 m3反铲装车20t自卸车配合拉运至填筑面.

(2)分区开采:料场根据开采时段、面积、数量、强度及机具不同,可将料场分作多个开采区,每个区以独立工作面分台阶(台阶高度4~5m)立面交替进行开采。

(3)料场排水:根据料场地形、降雨特点及使用情况,确定合理的排水标准,做出全面的排水计划。顺场地地势布置排水沟,并辅以支沟,排水系统与道路布置相协调。

3.3.4.料场开挖

(1)清表:砂砾料开采前,首先由220HP推土机进行水平清表.由1。

10

6m3挖掘机装料,20t自卸汽车拉运至弃渣场。

(2)全强风化料开采:主要由1。6m3挖掘机分层开采, 20t自卸汽车拉运至填筑区。

(3)施工机具配置:反铲挖掘机4台,20t自卸汽车10辆。

3.3.5.坝料加工

(1)过渡料加工

过渡料由20t自卸汽车从下库砂石料场运输至上库主坝料场转堆场;经现场掺配检测合格后,由3m3装载机装20t,自卸汽车运输至填筑作业面。

(2)排水料加工

排水料由下库砂石料场生产,3m3装载机收集、堆存、装车,填筑时3m3装载机装,20t自卸汽车运输至填筑作业面。

(3)反滤料加工

反滤料由下库砂石料场生产,堆放于过渡料附近,填筑时采用3m3装载机装,20t自卸汽车运输至填筑区。

3.3.6.料源平衡

本工程主坝坝体填筑总量53万m3,其中过渡料2.7万m3,反滤料9027m3,排水料34383m3,全强风化料44。7万m3。

除全强风化料外,所有填筑料均来自下库砂石料料场。

坝体全强风化料填筑总量44.7万m3,全强风化料自然方到压实方系数取0.8,损耗按0.03计算,则全强料开采自然方为58万m3。3#、4#、5#料场目前可用料源为78万m3,能够满足上坝要求.

坝体过渡料填筑总量2。7万m3,过渡料在下库砂石料料场取料,运至

11

上库主坝转运堆存场进行掺配,目前上库转运堆存场已开始进行堆存备料。排水料填筑总量34383 m3,排水料由下库砂石料场生产,运至上水库主坝转运堆存场,下库砂石系统已开始排水料及反滤料的生产及储备,下水库砂石系统生产能力完全满足上坝填筑需求,坝料平衡计划见下表 :

坝体填筑料平衡计划表

序号 1 2 3 4 5 6 7 填筑类别 主坝坝体填筑 全强风化料 过渡料 反滤料 排水料 上游坝坡垫层料 上游坝坡干砌石 填筑范围 坝体下游 坝体上游 单位 万m3 万m3 填筑量 23 23 2。7 0。9 3.4 0.7 0。7 坝 料 料 源 4#、5#料场 3#、5#料场 下库砂石料场开采、加工 下库砂石料场开采、加工 下库砂石料场开采、加工 下库砂石料场开采、加工 工程开挖利用料及下库砂石料场开采、加工 备注 根据现场情况调配 根据现场情况调配 坝体上、下游 万m3 坝体下游 坝体下游 坝体上游 坝体上游 万m3 万m3 万m3 万m3 3.4.坝料运输

1、坝料由反铲挖装,20t自卸汽车运输,车辆相对固定,并经常保持车厢、轮胎的清洁,防止残留在车厢和轮胎上的泥土带入清洁的过渡料、排水体料、坝壳料填筑区。

2、过渡(反滤)料运输及卸料过程中,采取措施防止颗粒分离。运输过程中过渡料保持湿润,卸料高度不大于2m.

3、监理工程师认为不合格的过渡(反滤)料或坝壳料,一律不得上坝. 4、坝料运输车辆必须在挡风玻璃右上角标明坝料分区名称。 5、坝料运输时,车辆速度不得大于20km/h,载重量不得大于车辆的标定载重量。

12

3.5.基础面清理及验收

1、在坝基最终开挖线以下的所有坑槽和平洞,均按施工图纸的要求回填密实,防渗帷幕线钻孔亦予以封堵,外露的预埋钢管切除削平。

2、坝体填筑部位的全部基础处理工作,按施工图纸要求施工完毕。 3、坝体填筑的基础,进行四方联合验收,合格后,才能开始坝体填筑。

4、坝基中布置有观测设备时,在观测设备埋设完毕,并经监理工程师验收合格后,才能开始坝体填筑.

3.6.过渡(反滤料)填筑

1、在沥青混凝土心墙施工过程中,做到心墙和过渡层的任何断面都高于其上、下游相邻的坝体填筑料1~2层,并在心墙铺筑后,心墙两侧过渡层以外4m范围内坝壳料采用自行碾低频碾压密实,以防心墙局部受振畸变或破坏。

2、过渡(反滤)料填筑的位置、尺寸、材料级配、粒径范围符合设计图纸的规定。过渡(反滤)料采用“后退法”卸料。

3、沥青混凝土心墙两侧过渡料的填筑与沥青混凝土心墙填筑面平起。 4、过渡(反滤)料填筑与相邻层次之间的材料界线分明。分段铺筑时,必须做好接缝处各层之间的连接,防止产生层间错动或折断现象.在斜面上的横向接缝收成缓于1:3的斜坡。

5、过渡(反滤)料填筑与坝壳料连接时,可采用锯齿状填筑,但必须保证反滤(过渡)料的设计厚度不受侵占。

6、过渡料与心墙或坝壳交界处的压实可用振动平碾进行,碾子的行驶方向平行于坝轴线。

13

7、过渡料与岸边接触部位,先洒水后用振动平碾顺岸边进行压实。压不到的边角部位,用人工夯实,但其压实遍数按监理工程师指示作出调整。

8、在过渡料与基础和岸边及混凝土建筑物(心墙基座混凝土)的接触处填料时,不允许因颗粒分离而造成粗料集中和架空现象。

9、坝料运至坝面卸料后,及时摊铺,并保持填筑面平整,每层铺料后用水准仪检查铺料厚度,超厚时及时处理。

10、过渡料填筑前,用防雨布等遮盖心墙表面,防止砂石落入钢模内.遮盖宽度超出两侧模板各30cm以上.

11、过渡料因方量少,不能逐层检查进行时,严格按监理人批准的施工参数施工,并加强现场监督,不允许出现漏压现象。

3.7.全强风化料填筑

1、全强风化料的填筑,必须在坝基处理及隐蔽工程验收合格后,才能填筑。全强风化料需剔除较大粒径的不合格料,土料填筑前,先对料场堆存粘土料的含水率进行检测,若含水量偏大,可在土料堆存场就地进行翻晒,直至含水率达到上坝要求为止;若含水量偏低时,可将土料在坝体填筑区内摊铺后,再由洒水车进行均匀洒水,加水后的土料采用推土机松土器深翻掺合均匀。

2、自卸汽车卸料时,采用“进占法”卸料,也可用“后退法\卸料,堆料高度不大于1。5m.填料的纵横坡部位,优先用台阶收坡法,碾压搭接长度不小于1.5m,如无条件时,接缝坡度不陡于1:3。

3、岸坡处不允许有倒坡,防止大径料集中,其2m范围内,用较细全强风化料填筑,而且先于坝体填筑料填筑,此处施工按小面积施工法铺筑压实。

14

4、在铺好一层全强风化料后,布点测量其压实前高程,以确定铺料厚度,铺料厚度满足方可填发测量合格证进行全强风化料碾压。

5、全强风化料碾压质量重在过程控制,重点监控碾压遍数、振幅、行驶速度、碾轮搭接宽度.碾压参数根据现场碾压实验确定,碾压方向一般平行于坝轴线,岸坡一般沿坡脚进行.碾压完成后,再按布点测量其高程,以控制压实厚度。碾压后的表面平整度按0~±10cm控制,若出现0~±30cm的不平整现象,重新推平表面进行铺压。

6、全强风化料压实后,按规范要求由工地试验室取样,取样次数不小于10000m3~100000m3一次,且每层必须检查边坡结合部,检查合格后,出具碾压合格证,并组织三检。合格后,方可进行下道工序.

7、坝基全强风化料永久坡位置,每填筑3m厚进行测量放线,对坝坡进行修整,以保证边坡符合要求。

8、施工中积极推行全面质量管理,并加强人员培训,建立健全各级质量责任制。

9、全强风化料压实后,按施工规范规定,每填10000m3~100000m3取样1次。根据土工试验要求,采用环刀法或试坑法进行检测.碾压后取样结果满足设计要求,否则进行铺压,直至满足质量控制指标要求为止。

10、全强风化料中不允许夹杂粘土、草、木等有害物质。

11、全强风化料在装卸时特别注意避免分离,不允许从高坡向下卸料。 12、压实全强风化料的振动平碾行驶方向平行于坝轴线,靠岸边处可顺岸行驶。振动平碾难于碾及的地方,用小型振动碾或人工夯实,但其压实遍数按监理人指示作出调整.

15

13、岸边地形突变及坡度过陡而振动碾碾压不到的部位,适当修整地形使振动碾到位,局部可用振动板或振动夯压实.

14、全强风化料采取大面积铺筑,以减少接缝。

15、坝内安全监测仪器的单位埋设完成后,须经过监理工程师的批准才可进行上部坝壳料的回填。

16、在接合的坡面上.应配合填筑的上升速度,将表面松土铲除至已压实合格的土层为止。坡面须经刨毛处理,并使含水量控制在规定的范围内,然后才能继续铺填新土进行压实。

17、布置于坝体的临时运输道路,必须按照相应部位坝体填筑要求予以分层压实.否则应挖除,并重新碾压。

18、大大坝上游坡面遭受冲蚀、塌坡时,视破坏范围的大小进行回填、补齐。回填料应偏细,并采用薄层轻碾或人工夯实,但不得降低压实标准。回填区的坡面应超填20cm,以备削坡。

3.8.排水料填筑

1、排水体随坝体上升逐层填筑。

2、排水体采用大于5~40mm的碎石,要求石料质地坚硬.

3、排水料填筑的施工,将经挑选合格的石料运至每一填筑层上,沿着靠近岸坡的边缘堆成条带状,用推土机将其推至坝坡边缘,由测量配合定位,其外缘与设计坝坡线误差不超过±10cm。

3.9.特殊部位结合面处理 1、坝体与岸坡结合部填筑

坝体与岸坡接合部位包括坝体与原岸坡、坝体与心墙基座等,其接合

16

部位填筑时,坝体上下游边坡部位填筑每上升2 层,采用反铲按照设计坡比进行坡面修整,保证坡面平顺整齐。

2、坝壳料与过渡料搭接处施工

过渡料与坝壳料填筑,总体遵循平起施工,即:三层过渡料(层厚28cm)与二层坝壳料(层厚80cm)平起施工,并在最后一层填平后进行骑缝碾压。

3、 坝体分区交界面处理

过渡料与反滤料交界面的处理 先铺反滤料,再铺过渡料,其交接面大于10cm 的分离石料予以清除.

4、临时断面边坡的处理

对临时断面边坡采用台阶收坡法施工,后续回填时采用反铲对相应填筑层的台阶松散料挖除及修整、清除污染不合格料,待该层铺料碾压时,可进行搭接碾压,从而保证交接面的碾压质量。

5、上坝路与坝体结合部

坝区内采用坝体相同料区的石料进行分层填筑,填筑质量按相同区料的填筑要求控制。当坝体填筑上升覆盖该路段时,路两侧的松渣采用反铲分层挖除至相应填筑层,一起平料骑缝碾压。 坝区外侧路段与坝体接触部位,待该路段完成运输任务后,再采用反铲挖除,并清理松渣、整理。

6、坝内斜坡道路

随着坝体临时断面上升,坝内上、下游形成临时斜坡运输道路。坝内斜坡道路按纵坡10~15%设置。道路填筑料采用相同坝区的土料,填筑质量按同品种料要求进行铺料和碾压.当坝体填筑上升覆盖坝内临时斜坡道时,采用反铲将斜坡道路两侧的松散石料挖除到同一层面上,与该层填筑料同时碾

17

压。

7、坝体填筑横向搭接接缝的处理

根据其他沥青混凝土心墙施工经验,坝体搭接坡比采用1:3,主要包括沥青混凝土心墙、过渡层及坝壳料的搭接。在先期坝体填筑过程中,坝壳料、过渡料及沥青混凝土心墙料分层铺筑时形成1:3的“人造边坡”,后期坝体铺筑时,由1.2m3反铲沿坡脚处将先期所填筑的坝壳料1。0m范围内未压实区重新摊铺,并削成1:2的边坡,形成1。0m宽的预留台阶,上层坝料铺填时,将下层碾压面露出,台阶预留明显、整齐,随后期坝壳料填筑一并进行,并采用骑缝碾压,以确保接坡处碾压质量。

3.10.干砌石护坡的施工 1、干砌石护坡的施工方法

砌石体的石料采用工程开挖利用料及料场生产的石料,在堆石料中选取合格的块石作为干砌石材料。块石材料由自卸汽车直接从料场运至施工工作面。块石要求材质坚实新鲜,无风化剥落层或裂纹,其块状大小及块石的容重和湿抗压强度要满足设计要求。

干砌块石砌筑时必须挂线施工,砌体厚度不得小于设计要求,砌体应咬扣紧密、错缝砌筑、垫塞稳定、表面平整,并用大块石封边,严禁出现通缝、叠砌、浮塞和松动现象,施工严格按规范要求进行.

2、干砌石护坡的施工质量控制

(1).外观检查:砌体砌筑面的平整度和石缝大小、石块嵌紧的紧密度、沉降缝贯通等的外观质量进行控制。

(2).料石和毛石砌筑的尺寸和位置的允许偏差应在规范规定的范围之

18

内。

⑶。干砌石坡面平整度控制,由测量人员每2m高差进行放样检查,并且在坡面搭设木制样架,挂线控制坡面的平整度,确保干砌石坡面的外观质量。

3.11.沥青心墙施工

沥青心墙施工详见《海南抽水蓄能电站土建主体工程沥青混凝土心墙施工方案》。

4.雨季施工

4.1.雨季施工措施

本标段坝体填筑经历2016年雨季,为确保坝体在雨季正常施工,特制定如下施工措施:

4。1在坝体两岸高边坡的合适位置设截水沟,并结合施工道路排水沟排除雨季边坡来水至填筑面以外,根据施工条件采取。适当措施,如:防雨材料覆盖粘土填筑工作面、工作面边缘挖排水沟引流减少雨水渗入等,缩短雨后停工时间,如果遇到大雨,上下游面碾压成型的坝面应进行全面覆盖,减少雨水对碾压后土体的的影响。

4.2雨季坝体填筑施工,为防止雨水明流对坝面及坝坡的冲蚀,及时对运输上坝料摊铺、整平、碾压;在每一层坝面碾压后,使坝面形成向上、下游倾斜的坡面(坡度不陡于2%),以利水流顺畅排泄。

4。3雨季坝体填筑施工,对运输道路加强养护,及时清除路面障碍物及路基排水沟,排水通畅。对运输车辆,加强维修保养,确保机械的制动系统安全.

4。4沥青混凝土心墙施工期间若遇下雨,为防止雨水对已成型沥青心墙的侵蚀破坏,在墙顶面覆盖耐高温的帆布,以确保墙体成型质量,具体

19

见沥青防渗墙施工方案.

4.5汛期来临前,备足防汛物资。降雨来临之前,应将已平整但未碾压的松土层,用平碾快速碾压形成光面,防止雨水渗入。

4.6加强气象预报,提前最好防雨准备,正确掌握雨前停工,雨后复工的时机.当日降雨量大于5mm时,停止坝体填筑施工(因沥青混凝土不能施工)。

4。7摊、平、碾各工序控制措施

对拉运至坝面的坝料,应及时摊铺、整平、碾压,各工序安排要紧凑,尽可能做到当日上坝料当日碾压成型,严禁堆料和积料.对坝料中不可避免雨水冲刷坝料要及时对其予以剔除,如因下雨停工,复工前清理坝面积水后,监理工程师验收后方可复工。

4。8料场雨季施工开采时,堆存料尽量保证台阶立面开挖,防止雨水大面积渗入土体内,造成含水率过高,立面台阶开挖利于排水及后续施工。原装土料场开挖后形成直立面避免雨水冲刷渗入,周边及道路两侧设置排水沟,保证雨水能够顺利排出不对道路及土料产生太大影响。

4.2. 其它控制措施

对运输道路应加强养护,尤其防止路面湿滑现象发生,设专人对路面坑洞及边坡失稳工作的巡查.对运输车辆,加强维修保养,确保机械的制动系统安全。

1、加强设备检查、保养工作

2、对于施工人员做好雨季施工安全教育.

3、对施工人员做好雨季劳保品发放,如手套、安全帽、雨衣、雨鞋等。

20

4.3.雨期坝面排水措施

施工期坝体排水,本工程坝址区集雨面积较大,特别是雨季施工时遇暴雨天气,集中水流容易对岸坡交接处,特别是上游垫层区产生较大的冲蚀,因此在坝体填筑期间,要高度重视坡面及岸坡的排水措施。

岸坡上的排水带或开挖截水沟,将岸坡下泄的水流导向坝区以外,防止岸坡集中水流冲蚀填筑坝面。

在坝体的填筑过程中,始终保持上游坡面高于下游坡面,尽量避免坝面的集中水流流向垫层区。

在整个堆石坝施工期间,注意加强排水,使坝体下游侧的水位始终低于上游侧水位,防止出现“反渗\现象,保护上游坝体的施工期安全。

下雨期间不得进行心墙的施工,雨期停工前,心墙表面应铺设保护层,如帆布、彩条布等防雨覆盖物,复工前予以清除。

5.施工安全及质量保证措施

5.1.安全保证措施

项目部成立以项目经理为第一责任人的文明施工领导小组,其成员由项目常务副经理、各部门(单位)负责人及专职监督员组成。各施工队设兼职监督员,负责实施文明施工的各项监督检查。各施工队严格按施工组织设计及环境保护措施落实各项工作。

加强现场施工人员安全教育,在班前做好三工活动,在砌筑过程中配置专职巡查安全员、安全哨。机械操作手选择熟练工,并配置指挥人员。

警示标志完备、醒目,重点地段及恶劣天气,设置专项的安全防护设施。并在发包人允许的前提下,设置明显的企业施工标牌.

施工现场实行局部封闭管理,保持场容场貌的整洁;做好施工现场安全

21

保卫工作,采取必要的防盗措施,在施工现场建立和执行防火管理制度,设置符合消防要求的消防设施,并保持完好的备用状态。水电线路整齐完好。

采取有效措施控制施工过程中的各种粉尘,废气、废水、固体废弃物以及噪声、振动对环境的污染和危害.

职工队伍建设好。营造良好的与邻边居民和兄弟施工单位的友好关系。 有完备的管理条例,严格透明的执行制度.严格履行职工劳保福利政策要求,有完备的重大事故预防、应急、处理措施。

施工设备的使用、停放整齐有序;设备性能安全、可靠;操作人员证照齐全,规范操作。配备完善的设备检修、保养、清洁设施及制定严格的检修、保养、清洁责任制.

(9)合理的现场平面布置,科学的施工计划.严格完善的材料计划供应制度.实行材料定额管理,减少现场清理工作.成品、半成品堆放整齐有序。保持整齐、清洁的

工作环境,作到工完场清。

大坝填筑前,加强专业知识培训学习,使施工员、质检员熟练掌握质量控制标准、程序等,增强的理性与感性认识。

建立健全质量管理规章条例,建立相应的重奖重罚的激励机制。 填筑料上坝道路,要派专人维护,确保道路畅通,卫生干净。 对现场的排水设施和照明设施进行定期和不定期的检查和维修,确保排水的通畅,和供电的连续。

5.2.施工准备阶段质量保证措施 1、坝体基础面的清理与验收

22

对经基础开挖完成后的坝基面,按表中相关要求进行清理。

坝基与岸坡处理的质检项目及技术要求

项目 质量要求 按照设计图纸,对坝基最终开挖线以内的基础面进行测量,绘制纵、横断面坝基断面验收 图,以便计坝体填筑算分期(序)工程量。 地质钻孔深坑、平洞 无遗漏,处理符合设计要求。 ①草皮、树根、乱石及各种建筑物等全部开挖清除,符合设计要求; ②按设计要求清除覆盖层; 坝基部位 ③岩基处理(包括断层)符合设计要求; ④坝基面无积水. ①开挖坡度和表面清理符合设计要求; 岩坡部位 ②开挖坡面稳定,无松动块、危石及孤石; ②凹坑、反坡已按设计要求处理。 2、坝基基础范围内埋设观测仪器设备保护对坝基范围内布置的观测设备,设醒目标志,设专人负责监护,以免破坏。

3、坝料开挖为防止坝料在开挖运输过程中发生粗料集中现象,各类坝料在开挖中,以立面开采为主。

4、坝料运输

(1)坝料运输采用自卸汽车,运输车辆相对固定,并经常保持车厢、轮胎的清洁,防止残留在车厢和轮胎上的泥土带入清洁的反滤料、垫层料、过渡料、排水体料和坝壳料的料源及填筑区。

(2)坝料运输车辆必须在挡风玻璃右上角标明坝料分区名称。 (3)坝料运输时,车辆速度不得大于20km/h(桥梁处不大于15km/h),载重量不得大于车辆的标定载重量。

23

(4)对雨季坝料运输道路,设专人对路面进行养护,并在道路旁作醒目标志;

5.3.坝体填筑过程质量保证措施 1、过渡料填筑

(1)在沥青混凝土心墙施工过程中,心墙和过渡层都高于其上、下游相邻的坝体填筑料1~2层,并在心墙铺筑后,心墙两侧过渡层以外2m范围内采用22t自行式振动碾压实坝壳料,以防心墙局部受振畸变或破坏。

(2)过渡料填筑的位置、尺寸、材料级配、粒径范围符合设计图纸的规定。紧邻心墙的过渡料采用摊铺机摊铺,其余过渡料采用“后退法\卸料。

(3)沥青混凝土心墙两侧过渡料的填筑与沥青混凝土心墙填筑面平起。

(4)过渡料填筑与相邻层次之间的材料界线分明。分段铺筑时,必须做好接缝处各层之间的连接,防止产生层间错动或折断现象。在斜面上的横向接缝收成缓于1:3的斜坡.

(5)过渡料填筑与坝壳料连接时,采用锯齿状填筑,但必须保证过渡料的设计厚度不受侵占。

(6)为增强压实效果,过渡料碾压前做加水润湿试验,根据试验结果确定是否加水及加水量。

(7)过渡料与心墙或坝壳料交界处的压实可用振动平碾进行,碾子的行驶方向平行于坝轴线。

(8)过渡料与岸边接触处可用振动平碾顺岸边进行压实。压不到的边角部位,采用人工夯实,但其压实遍数按监理工程师指示作出调整.

24

(9)在过渡料与基础和岸边及混凝土建筑物接触处填料时,不允许因颗粒分离而造成粗料集中和架空现象。

(10)坝料运至坝面卸料后,及时平整,并保持填筑面平整,每层铺料后用水准仪检查铺料厚度,超厚时及时处理。

2、全强风化料填筑

(1)全强风化料的填筑,在坝基处理及隐蔽工程验收合格后,才能填筑。

(2)自卸汽车卸料时,用“进占法”卸料,也可用“后退法”卸料,堆料高度不大于1。5m.填料的纵横坡部位,优先用台阶收坡法,碾压搭接长度不小于1。5m,如无条件时,接缝坡度不陡于1:2。

(3)岸坡处不允许有倒坡。

(4)在铺好一层坝壳料后,布置测点,测量其压实前高程,以确定铺料厚度,铺料厚度满足方可填发测量合格证进行坝壳料碾压.

(5)坝壳料碾压时重点监控碾压遍数、振幅、行驶速度,碾压方向一般平行于坝轴线,岸坡一般沿坡脚进行。碾压完成后,定点测量其高程,以控制压实厚度。碾压后的表面平整度按0~±10cm控制,若出现0~±30cm的不平整现象,重新推平表面进行铺压。

(6)坝壳料压实后,通过工地试验室取样,取样数量不小于10000m3~100000m3一个,且每层必须检查边坡结合部,检查合格后,发给碾压合格证,并组织三检。合格后,方可进行下道工序。

(7)每填筑3m厚进行测量放线,对坝坡进行修整,以保证边坡符合要求。

25

(8)施工中积极推行全面质量管理,并加强人员培训,建立健全各级质量责任制.

(9)坝壳料中不允许夹杂粘土、草、木等有害物质。

(10)坝壳料在装卸时特别注意避免分离,不允许从高坡向下卸料。靠近岸边地带以较细石料铺筑,严防架空现象.

(11)坝壳料铺料和碾压过程中的加水量由试验确定.

(12)压实坝壳料的振动平碾行驶方向平行于坝轴线,靠岸边处可顺岸行驶.振动平碾难于碾及的地方,用小型振动碾或人工夯实,但其压实遍数按监理人指示做出调整。

(13)岸边地形突变及坡度过陡而振动碾碾压不到的部位,适当修整地形使振动碾到位,局部可用振动板或人工夯实.

(17)坝体坝壳料采取大面积铺筑,以减少接缝.当分块填筑时,对块间接坡处的虚坡位置采取专门的处理措施,如采取台阶式的接坡方式等。

3、排水棱体料

(1)大坝下游排水棱体的填筑,随坝体上升逐层填筑。 (2)排水料要求石料质地坚硬,平均块径符合施工图纸规定。 (3)排水体施工时,将合格的卵石运至每一填筑层上,沿着靠近坝坡的边缘堆成条带状,用推土机将其推至坝坡边缘,由测量配合定位,其外缘与设计坝坡线误差不超过±10cm。

5.4.总体质量保证措施

严格控制上坝填筑材料,不合格的料禁止装运及上坝。

严格按试验确定的填筑碾压参数施工,各个工序必须经验收签证后方

26

可进入下一道工序,不合格的工序严禁进入下一工序。

质量检测以控制碾压参数为主,以试坑注水法抽样检测为铺的“双控\措施,并充分利用发包人提供的GPS 信息管理系统,做好坝体实体质量控制。

通过强化的检测手段对大坝填筑料的料场和坝体填筑结果,按抽样方法进行抽样,进行干密度和填料级配检测试验,抽样频率按规范设计要求实施.

配备先进的试验、检测仪器设备,调配精干的试验检测人员到施工现场,对填筑质量实施监控。

用参数控制记录值、检验结果以及外观检查三个方面对填筑单元质量进行评定.

使用统计技术对参数记录、试验分析结果进行统计分析,针对存在的问题,有针对性地提出改进措施,不断提高质量控制水平。 施工质量和安全保证措施

成立以项目经理为第一责任人的质量管理机构,下设各专业质量责任组,如坝体填筑、料场挖装、骨料制备等责任组,分工明确,各负其责.

每月召开质量管理例会,不定时请发包人、设计、监理进行质量检查,及时分析出现的质量控制薄弱环节,严格按照ISO9000 质量体系制定纠正、预防措施.

根据土石坝施工经验及本工程特性,设立质量控制关键点,并下发宣传至作业班组.

每隔一定时间,依据试验检测数据,及时采用数理统计分析,分析出

27

偏差原因,及时整改.

运输各填筑区料的车辆要相对固定,经常保持车厢、轮胎清洁,防止残留的污染物带入清洁的料源和填筑区。

5.5.各类坝料填筑检查项目及取样次数、控制标准和碾压机械技术性能

表8-4-1 坝料压实检查项目及取样次数表

部位 过渡层区 排水反滤区 坝壳料 说明 检查项目 干密度、颗粒级配 干密度、颗粒级配、含泥量 干密度、颗粒级配 抽样检验次数 1次/500m3~1000m3,每层至少一次 1次/200m3~500m3,每层至少一次 1次/10000m3~100000m3,每层至少一次 《碾压式土石坝施工规范》(DL/T5128-2001)

表8—4-2 可利用料、坝壳料控制标准及施工参数

控制标准 料种 干密度(g/cm3) 坝壳料 碾压报告 孔隙率压实度 (%) / ≥0.98 度(cm) 40±8 数(遍) 10 铺料厚碾压遍振动碾工况 量 施工参数 洒水表8—4—3 碾压机械技术性能参数表 机械类别 前进 行进速度(km/h) 后退 振动频率(Hz) 振幅(mm) 激振力(kN) 钢轮宽度(mm) 3~4 30 1。8 330/190 2180 22T自行振动碾 3~4 5.6.坝体质量控制关键点 项目 关键控制点 采取措施 28

预防、纠正措施

在料场出口处设立质量检查站,不合格者退回级配的合理性, 经常巡视开挖掌子面,料场;坝面填筑时, 及回采料场 挖装时不得集中发现级配不均的, 要求时调整卸料次序,使得细料或粗块料 混装,超径严重的剔除. 粗细料子在平整过程中掺合。 料源 石料的加工筛分对筛分系统进行检查,石料加工级配合理性,转检查筛分系统及转级配拒绝发生混料或级配不料场 级配及堆存场的时的检查 。 良的现象。 控制 料源制备层厚、采用定点测量控制铺料经常进行施工员、挖装含水率控制,出层厚; 挖装前及时快速人员技术交底; 配置现掺合料场 场前的含水量控检测含水量,必须边混场试验人员,制定含水制及装料级配。 量调整措施。 边装。 料源 土料场 含水量控制 及时检测及时调整开挖掌子面。 根据坝面检测结果对症采取措施。 项目 碾压 关键控制点 设备激振力, 碾压遍数、碾迹重叠宽度、有无漏碾 采取措施 按期进行设备率定,质检员不定时抽查,层面验收时重点检查边角部位。 预防、纠正措施 施、检人员巡视旁站监控员,根据仪器检测,保证碾压参数。 坝面 摊铺 层厚 坝面 运输 严格区分分区料源 每隔一定高程进行填坝材料采取全站仪层面找平等调整措定点测量,堆石体采施,尽量使实际施工用活动标竿等措施。 层数与理论层数一致。 每个料场在一定时间基本固定运输车辆,加强对运输人员、卸每车辆在明显位置挂料指挥人员料源识标识牌,每天做好运别培训,坝面入口检输规划,坝面设置卸查并作相应调整。 料指挥人员。

29

试验检测合格率,有无漏碾,单元验收 层面处理是否满足要求,接缝处理是否满足要求。 取样位置及取样频率 指定专职质检员进行过程监督, 对边角、不合格部位重新返接缝、防渗体路口段工处理至合格为止。 处等专项检查。 取样试验 必须随机性位置,每天计算填筑工程量与低于设计要求必须取样频率进行对比。 重新碾压处理。

6.施工进度计划及工期保证措施

6.1.施工进度计划

根据施工总体规划,主坝填筑计划日进行主坝填筑,历时。

主坝填筑控制工期表

部位 主坝

高程(m) 填筑时段 历时(月) 工程量(万m3) 6.2.施工强度分析 坝体填筑强度分析

主坝填筑强度表

部位 主坝 填筑高程 填筑时间 工程量 分期平均强度 分期高峰强度 主坝填筑总量为53万m3,实际有效施工期共4个月,平均强度约为13。3万m3/ 月,高峰强度20.3万m3。其中全强风化料填筑强度为43.6万m3,每月按25个有效工作日,平均每天需填全强风化料6100m3。 1、沥青心墙施工强度分析

根据施工高峰期强度分析,沥青施工日最高强度为70m3(按每月20天有效施工日)。施工设备配备:20m3/h的沥青拌和楼;1台沥青摊铺机,1

30

台小型震动碾;2台3 m3沥青混凝土料运输车. 2、坝体全强风化料填筑强度分析

高峰期月最大填筑强度为164250m3,日最高强度为8200m3(按每月20天有效施工日)。

1)、料场挖桩采设备投入:

挖装设备采用PC400反铲挖掘机,每台按1200m3/台班,每天按两个台班计,8200/(1200×2)≈4台。

2)、运输设备:采用15t自卸车,2km运距每台车辆运输量按150m3/台班,每天按两个台班计,8200/(150×2)≈27台,取30台。

(3)、平整碾压设备投入:

① 土料平整设备:D7推土机,每台按1800m3/台班,每天按两个台班计,8200/(1800×2)≈2台,挖掘机配合。

② 碾压设备:22t振动碾(行驶速度2~5km/h),碾压按3000m3/台班,每天按2个台班计,8200/(3000×2)≈2台,取3台。

全强风化料填筑设备配备表

序号 1 2 3 4 5 设备类型 反铲挖掘机 反铲挖掘机 自卸汽车 推土机 振动碾 型号 PC400 PC200 15t D6、D7 22t 单位 台 台 辆 台 台 数量 2 2 30 2 3 备注 料场 坝面整理 两用1备 3、过渡料、上游坝坡垫层填料填筑设备

月高峰强度24448m3,日最高强度为1222m3(按每月20天有效施工日)。 (1)、装车设备:中转料仓装料,装载机,2台。

(2)、运输设备:采用15t自卸车,2.0km运距每台车运输量按300m3/

31

台班,每天按两个台班计, 1222/(300×2)≈2台,取3台.

(3)、平整碾压设备投入:

① 平整设备:采用1台3。0m3轮式装载机,人工辅助摊铺. ② 碾压设备:过渡料碾压与沥青料同步,配2台小型震动碾,上游坝坡垫层震动碾与大坝全强风化料同步碾压。

过渡料、上游坝坡垫层料填筑设备配备表 序号 1 2 3 设备类型 轮式装载机 自卸汽车 震动碾 型号 3.0m3 15t 2.5t 单位 台 辆 台 数量 3 3 2 备注 4、施工高峰期总设备表

施工施工高峰期总设备表

序号 1 2 3 4 5 6 7 8 设备类型 反铲挖掘机 反铲挖掘机 轮式装载机 自卸汽车 推土机 震动碾 沥青摊铺机 小型震动碾 型号 PC400 PC200 3.0m3 15t D7 22t 单位 台 台 台 辆 台 台 台 数量 3 2 3 33 3 3 1 3 备注

6.3.工期保证措施

为确保工期,保质保量地完成施工任务,必须进行周密的计划和合理的组织,保证工程如期完成,在施工中,我们采取如下保证措施:

①、组建一个高效务实的施工领导班子,集中管理统一调度.由现场管理组长统一指挥,对施工机械,技术人员统一调度,最大限度地满足本工程需要。

32

②、施工时制定详细的各分项工程的施工技术措施、组织流水作业,做到技术先进,工艺合理。

③、每月、每周指定详细的施工进度计划,专人负责执行,做到计划科学合理,施工认真到位,并在施工过程中不断予以优化,力争提前完成本工程的施工.

④、根据工程情况分成几个工作面,各段任务责任到人。合理安排劳动力,做好现场组织工作。

⑤、确保设备、人力、物力充足。必要时增加劳动力,加班加点,保质量,抢工期.

⑥、制定各施工项目用料的供应计划及机械使用计划,确保材料供应及时到位,满足施工要求。并存有备料,确保不因材料短缺而影响工期。

⑦、根据各施工段情况编制出施工网络图,抓住关键线路,保证各工序顺利施工,关键工序施工时严格控制其进度,必要时增加劳动力和机械设备。认真制定各工序之间的衔接计划措施,缩短上下工序的衔接时间.

⑧、加强质量监督,避免工程返工,严格按图纸规范施工,对单元工程及时进行质量自检、互检、验收评定,提高验收一次成功率,避免因返工延误工期。

⑨、与项目部、业主、监理、设计部门与其他施工队伍协调好工作,处理好当地群众的关系。减少工作纠纷,加强配合.

7.资源配置

7.1.管理人员配置

主要管理人员

序号

姓名 职务 33

职称 备注 1 2 3 4 5 6 7 8 9 10 项目常务经理 项目副经理 项目总工 项目副总工 质检部长 测量班长 试验班长 总调 调度 安全部长 高级工程师 高级工程师 高级工程师 工程师 助理工程师 助理工程师 7.2.劳动力安排

施工劳动力安排计划

工 种 现场管理人员 技术员 试验员 测量工 砌石工 重机工 司 机 修理工 电 工 普通工 合 计 人 数 5 6 3 4 30 10 30 5 3 10 106 备注 7.3.施工机械设备的配置

施工机械设备一览表

设备名称 挖掘机 推土机 自行碾 型号或 规格 PC400 D6/D7 22t 数量 7台 4台 3台 检修 情况 良好 良好 良好 备注

34

装载机 自卸汽车 蛙式打夯机 水 泵 测量仪器 3m3 20t HW-60 3BA-13A 3台 33辆 3台 2台 1套 良好 良好 良好 良好 良好 8.安全文明生产及环境保护措施

8.1.料场

对本标段而言,主要存在回采料场及开挖料场。

1、界定料场开采范围,其四周设立隔离带,避免非生产人员及牲畜进入开采区,确保开采区施工安全。

2、料场开采区,各设立1个标志牌,注明开采单位、负责人姓名、质检人姓名及料场主要用途、面积、数量及时段等。

3、砂砾石料场开采拟分层进行,为防止雨水造成边坡坍塌,对边坡进行临时加固处理,以保证边坡稳定.

4、对料场开采弃料,如清表等,有序堆放,并定期喷洒水作好扬沙除尘工作,以备二次利用。

5、对运输道路,其坡比不陡于10%,局部地段不陡于12%。道路维护作好洒水除尘工作。

6、料场开采期,要做好现场的文明施工,随时清理废弃物,做到无积水、无杂物、无废旧不用材料,工作面干净整洁.在料场开采完成后,要遵守“工完、料尽、场地净”的原则,完成一处,清理一处,不留垃圾,不留剩余施工材料和施工机具。

8.2.坝料运输 1、运输车辆

35

(1)自卸汽车作为本标段坝体填筑料的主要运输工具,为保证上坝料物按秩有序进行,每辆运输车辆必须在挡风玻璃右下角粘贴坝料类别卡片,卡片尺寸为30×40cm。

(2)运输车辆要相对固定,并保持车体干净卫生,尤其对特殊垫层料、垫层料、过渡料、反滤料及排水料更应保证运输车辆干净,防止在坝料运输中对坝料造成污染。

(3)运输车辆设加高挡板,但装渣量不得超过额定重量,以防沿途掉渣。 (4)运输车辆在运输过程中,车速不大于20km/h(桥梁处不大于15km/h),并严禁超车,做到礼貌行车,不挤抢车道。

(5)运输车辆司乘人员要遵守《中华人民共和国道路交通管理条例规定》,并加强车辆的维修保养,遵守发包人对施工场区运输车辆管理规定。 2、运输道路

(1)对坝外运输道路,设立道路标志牌,并注明前方到站地点名称、公里里程。

(2)对开挖与填筑运输道路,其坡比不陡于10%,局部地段不陡于12%。道路维护作好洒水除尘工作。

(3)因本工程坝体填筑运输车辆,分别通过上、下游及右岸施工道路上坝,故现场车辆交错,其交通秩序派专职人员统一管理.

(4)对本标段所修建交通道路路面上的石渣、垃圾等每4h清理一次;路边石渣、垃圾等每周清理一次;道路排水沟不得有积水杂物。

(5)对本标段所修建道路路面平整、无积水;若道路有所毁坏,在24h内恢复。

36

8.3.坝料填筑

(1)坝体填筑采用分序上升,坝面要平整,相邻坝体分区间高差不得大于一层坝料的高度;

(2)坝体填筑期,每层坝面上设有坝体分区的标识牌,并注明填筑料物名称;对正在施工的坝面区,设立各类坝料所处工作状态,如上料、碾压、质检、合格、待检等标识牌;用红色油漆在两岸坝肩上标明坝轴线、各区料填筑桩号及分序高程等;

(3)坝体填筑期,要积极配合设计、地质人员,为其工作提供方便; (4)为确保坝体填筑期上、下游边坡安全,按坝体每升高20m要求,在边坡区设置一层安全防护栏,防护栏采用成品钢板网;

(5)对坝面设立的临时值班室,门前均设置“保洁箱”,垃圾一律入内,并及时清理到指定位置;

(6)为防止坝面施工人员随意丢弃垃圾,在每层坝面设立“保洁箱\,并由专人负责清理移位工作,以保证坝面干净整洁.

9.强制性条文

《水利水电工程施工组织设计规范》SDJ338-1989

6.2.5做好土石挖填方平衡,统筹规划堆、弃渣场地,充分利用开挖渣料;如需弃渣,应符合环保要求,在河边弃渣应不影响河道行洪和抬高下游尾水位。

7。5.1碾压式土石坝施工进度应根据导流与安全度汛要求安排,研究坝体的拦洪方案,论证上坝强度,确保大坝按期达到设计拦洪高程。 《碾压式土石坝施工规范》DL/T 5129-2001

5.4。3大坝施工期间,必须保证按照施工总进度要求,达到度汛的形象

37

面貌,严禁降低度汛安全标准。

5。4.5施工期间,当遭遇非常洪水、大坝或泄洪设施的技术状况恶化、使工程的安全受到威胁时,必须及时向上级防汛机构准确报告险情,并提出紧急处理措施,进行紧急处理.

6。0.11防渗体和反滤过渡区部位的坝基和岸坡岩面的处理,包括断层、破碎带以及裂隙等处理,尤其是顺河方向的断层、破碎带必须按设计要求作业,不留后患。

9.1.1坝料必须在符合设计要求的料场或建筑物开挖区及堆料场内采运,不合格的材料不得上坝。

10。1.5防渗体填筑时,应在逐层取样检查合格后,方可继续铺填。反滤料、坝壳沙砾料和堆石料的填筑,应逐层检查坝料质量、铺料厚度、洒水量,严格控制碾压参数,经检查合格后,方可继续填筑。

10。3。9防渗体与两岸接坡及上下游反滤料必须平起施工。防渗体填筑及雨后复工时,经检查合格后,方可继续填筑。

10.3。10雨后复工处理要彻底,首先人工排除防渗体表层局部积水,并视未压实表土含水率情况,可分别采用翻松、晾晒或清除处理.严禁在有积水、泥泞和运输车辆走过的坝面上填土。 11.0。4防渗体与坝基结合部位填筑:

1、对于黏性土、砾质土坝基,应将表面含水率调整至施工含水率上限,用凸块振动碾压实,经监理工程师验收合格后方可填土。

2、对于无黏性土坝基铺土前,坝基应洒水压实,经监理工程师验收合格后始可根据设计要求回填反滤层和第一层土料.

38

11。0。5防渗体与岸坡结合部位填筑:

1、防渗体与岸坡结合带的填土宜选用黏性土,其含水率应调整至施工含水率上限,选用轻型碾压机具薄层压实,局部碾压不到的边角部位可使用小型机具压实,严禁漏压或欠压。

2、防渗体结合带填筑施工参数应由碾压试验确定. 3、防渗体与其岸坡结合带碾压搭接宽度不应小于1.0m.

4、如岸坡过缓,结合处碾压后土料因侧向拉移,若出现“爬坡、脱空”现象,应将其挖除。

11。0.6防渗体与混凝土面或岩石面结合部位填筑:

1、填土前,混凝土表面乳皮、粉尘及其上附着杂物必须清除干净。 4、填土与混凝土表面、岸坡岩面脱开时必须予以清除。

6、混凝土防渗强顶部局部范围用高塑性粘土回填,其回填范围、回填土料的物理力学性质、含水率、压实标准应满足设计要求.

12。1。9严禁在反滤层内设置纵缝。反滤层横向接坡必须清至合格面.使接坡反滤料层次清楚,不得发生层间错位、中断和混杂。

14。3.1各种坝料质量应以料场控制为主,必须是合格坝料才能运输上坝,不合格材料应在料场处理合格后才能上坝,否则应废弃.

14.4。5防渗体填筑时,经取样检查压实合格后,方可继续铺土填筑,否则应进行补压.补压无效时,应分析原因,进行处理。

14.4。6反滤料和过渡料的填筑,除按规定检查压实质量外,必须严格控制颗粒级配,不符合设计要求应进行返工。

14。4。7坝壳堆石料的填筑,以控制压实参数为主,并按规定取样测定干

39

密度和级配作为记录。每层按规定参数压实后,即可继续铺料填筑.对测定的干密度和压实参数应进行统计分析,研究改进措施.

14.4。8进入防渗体填筑面上的路口段处,应检查土层有无剪切破坏,一经发现必须处理。

14。4。13雨季施工,应检查施工措施落实情况。雨前应检查防渗土体表面松土是否已适当平整和压实;雨后复工前应检查填筑面上土料是否合格。

40

【施工方案】大坝填筑施工方案

目录1。概述··············································································11.1。工程概况·································································11.2。编制依据
推荐度:
点击下载文档文档为doc格式
9a9ml5wlan6b8ve00zsa83uyx967u500vda
领取福利

微信扫码领取福利

微信扫码分享