框架剪力墙结构办公楼施工组织设计

天下 分享 时间: 加入收藏 我要投稿 点赞

目 录

第一章 编制依据和原则 ····················································1

1.1编制依据 ................................................................................. 1 1.2编制原则 ................................................................................. 1 第二章 本工程采用的技术规范、规程和标准 ··························2 第三章 工程概况 ····························································3

3.1工程设计特点 .......................................................................... 4 3.2施工条件 ............................................................................... 17 第四章 施工部署 ·························································· 19

4.1工程总目标 ............................................................................ 19 4.2施工组织机构和施工人员配备 ............................................... 19 4.3施工任务的分工 ..................................................................... 21 4.4施工准备工作 ........................................................................ 22 4.5施工顺序安排 ........................................................................ 24 第五章 专项施工方案编制计划 ········································· 25 第六章 施工方案 ·························································· 26

6.1施工机械设备的选用 ............................................................. 26 6.2分部分项工程施工方案 .......................................................... 27 6.2.1测量放线 ............................................................................. 27 6.2.2基坑支护及土方开挖方案(另编专项施工方案) ............... 29 6.2.3基础、地下室、主体结构工程 ............................................ 45 6.2.4装饰工程 ............................................................................. 81 6.2.5外墙玻璃幕墙工程(另编制专项施工方案) ....................... 95 6.2.6门窗工程 ............................................................................. 97 6.2.7聚氨酯防水外墙施工方法 ................................................... 99 6.2.8±0.000以上屋面工程 ......................................................... 100 6.2.9电气安装工程 ................................................................... 110 6.2.10给水、排水安装工程 ....................................................... 122 6.2.11通风与空调工程 .............................................................. 134

1

6.2.12外脚手架施工方案(另编制专项施工方案) ................... 144 第七章 施工进度计划及保证措施 ······································ 153

7.1施工进度安排原则 ............................................................... 153 7.2施工进度计划 ...................................................................... 154 7.3保证进度计划的措施 ........................................................... 154 第八章 保证质量措施 ···················································· 157

8.1质量目标 ............................................................................. 157 8.2工程质量保证体系 ............................................................... 157 工程质量保证体系图如下: ...................................................... 158 8.3质量控制程序 ...................................................................... 159 8.4施工过程质量控制工作 ........................................................ 159 8.5各分部分项工程质量保证措施 ............................................. 162 8.5.1测量定位质量保证措施 ..................................................... 162 8.5.3基础、地下室工程质量保证措施 ....................................... 163 8.5.4模板工程质量保证措施 ..................................................... 165 8.5.5钢筋工程质量保证措施 ..................................................... 167 8.5.6砼工程质量保证措施 ......................................................... 168 8.5.7砌筑工程质量保证措施 ..................................................... 170 8.5.8装饰工程质量保证措施 ..................................................... 171 8.5.9楼地面工程质量保证措施 ................................................. 175 8.5.10门窗工程质量保证措施 ................................................... 176 8.5.11给排水工程质量保证措施 ................................................ 178 8.5.12电气工程质量保证措施 ................................................... 179 8.5.13屋面工程的保证质量措施 ................................................ 179 8.6常见质量通病防治措施 ........................................................ 180 8.6.1土方工程质量通病及防治措施 .......................................... 180 8.7工程半成品及成品保护 ........................................................ 192 第九章 施工现场平面布置 ·············································· 194

9.1施工生产设施布置 ............................................................... 194 9.2施工供电及供水、排水布置 ................................................. 195

2

9.3通讯 ..................................................................................... 199 第十章 施工机械的进退场计划 ········································· 200 第十一章 工程材料的进场计划 ········································ 202 第十二章 劳动力计划表 ················································· 203 第十三章 冬、雨季施工措施 ··········································· 204

13.1冬季施工措施 .................................................................... 204 13.2雨季施工措施 .................................................................... 204 第十四章 其他地上地下设施的加固保护措施 ······················· 205 第十五章 保证安全生产措施 ··········································· 205

15.1安全承诺 ............................................................................ 205 15.2安全管理程序控制 ............................................................. 205 15.3建立和健全安全保证体系 .................................................. 206 15.4安全教育 ............................................................................ 207 15.5施工安全技术交底 ............................................................. 208 15.6现场管理规定 .................................................................... 208 15.7安全检查 ............................................................................ 209 15.8特殊工种持证上岗 ............................................................. 209 15.9深基坑、边坡支护和防护安全技术措施 ............................. 209 15.10高空作业及立体交叉作业的防护、保护措施 .................... 209 15.11安全用电和机电设备的防护、保护措施 ........................... 210 15.12机械设备操作安全措施 .................................................... 211 15.13防火防爆措施 ................................................................... 213 15.14预防自然灾害的措施 ........................................................ 214 15.15脚手架规定 ...................................................................... 214 15.16管理规定 .......................................................................... 215 第十六章 文明施工措施 ················································· 215

16.1建立和健全文明施工保证体系 ........................................... 215 16.2施工现场管理 .................................................................... 215 16.3文明卫生管理 .................................................................... 216

3

16.4做好保健急救工作 ............................................................. 217 16.5环境保护措施 .................................................................... 217 第十七章 工程服务及保修措施 ········································ 219

17.1实施的目的 ........................................................................ 219 17.2公司相关部门的职责 .......................................................... 219 17.3工作程序 ............................................................................ 220 17.4项目产品保修 .................................................................... 220 17.5保修后的处理 .................................................................... 221 第十八章 新技术、新工艺、新材料采用情况 ······················· 221 第十九章 附图 ··························································· 223

4

第一章 编制依据和原则

1.1编制依据

1.1.1现行国家和有关主管部门制定的有关方针、政策、法律、法规、规章、规范及其强制性条文、规程、标准、定额、建筑施工手册。

1.1.2工程设计施工图及其标准图(包括设计变更、图纸会审记录、设计交底等设计文件)、地质勘察报告、建筑工程施工合同(包括补充协议、投标文件等)。

1.1.3公司制定的ISO9001-2000程序文件、企业标准以及广西XX集团XX建筑工程有限责任公司《管理手册》Q/GXWJ/QEO-SC-2005和《程序文件》Q/GXWJ/QEO-CX-2005、《作业文件》Q/GXWJ/QEO-ZY-2005以及《作业指导书》及有关文件资料。

1.1.4类似工程施工经验及新技术、新工艺、新材料、新设备应用成果。

1.2编制原则

1.2.1严格执行基建程序、发挥本公司技术优势,全面执行公司“精心施工,顾客满意,节能降耗,环境和谐,安全健康,预防为止,诚信守法,持续改进”,尽快发挥业主的投资效果。

1.2.2科学地安排施工顺序,采用平行流水作业法组织施工,保证施工的连续性和均衡性,充分发挥人力、物力作用。

1.2.3合理利用先进的机械设备,减轻劳动强度,提高劳动生产率,加快工程施工进度。

1.2.4坚持质量第一,全面执行ISO9001-2000国际标准化管理体系和新技术、新工艺、新材料、新方法成果的应用,确保工程质量和安全,切实贯彻执行国家施工验收规范、操作规程和制度。

1.2.5加强工程进度的科学性、计划性的管理,合理安排机械、材料、劳动力的进退场,确保现场文明、整洁及工程的正常施工。

1.2.6发挥“团结、务实、拼搏、创新”的企业精神,坚持质量第一、用户至上的宗旨。

1.2.7遵循国家及南宁市有关环保精神,采取有效措施,减少环境污染,降

框架剪力墙结构办公楼施工组织设计