装置布置工程规定 1 of 16
北京中寰工程项目管理有限公司 Beijing Zhonghuan Engineering & Project Management Co., Ltd. 项目名称:Phifer LTD Ningbo Plant 飞佛特种纺织品(宁波)有限公司项目 装置名称: 资质等级 : 乙级 证书编号 :011053-sy 文件号 XXXXX
ENGINEERING SPECIFICATION
FOR
PLANT LAYOUT 装置布置工程规定
C0 修改 REV FOR CONSTRUCTION 说 明 DESCRIPTION 王生勇 编制 PRE’D 校核 CHK’D 审核 APP’D 审定 AUTH’D 项目经理 日期 PROJ.MAN DATE 装置布置工程规定 2 of 16
Table of Contents
目录
1. General
2. General Consideration 3. Site Layout
4. Arrangement Of Equipment 5. Pipeways
6. Accessways
7. Safety Distance Guide
(中文)
1. 概述 11 2. 总则 11
3. 现场布置 12 4. 设备布置 13 5. 管廊 14 6. 通道 14 7. 安全距离导则 15
3
3 5 6 8 8 9
装置布置工程规定 3 of 16
1. GENERAL 1.1 Scope
(1) This specification covers the requirements of the layout of process unit
and associated facilities and also for the spacing of equipment and structures to provide for safe and easy operation, maintenance and construction in Phifer LTD Ningbo Plant.
(2) Clearance and access for operation and maintenance of equipment
furnished as a regular part of proprietary equipment (or package unit) may be in accordance with the equipment manufacturer standards.
1.2 Codes and Standards
The following codes and standards shall be applied to this specification. (1) GB50160-92: Fire Prevention Code of Petrol Chemical Enterprise Design
(2) HG20546-92: Design Standard Equipment Layout for Chemical Plant 1.3 Related Engineering Specifications
5084-000-00-PP0202: Engineering Specification for Piping Design 1.4 Units
Unless otherwise specified, metric, Celsius units shall be applied as the measurement system. Nominal sizes of piping shall be in accordance with inch system (\
2. GENERAL CONSIDERATIONS 2.1 Site Conditions
For layout study, following site conditions shall be taken into account. (1) Geological condition (2) Wind direction
(3) Environment conditions (4) Utilities
(5) Climatic conditions