箱涵模板施工方案
编制: 审核: 审批:
项目经理部
2013年 9 月
目 录
1 编制依据 ............................................................................................................................ 1 2 工程概况 ............................................................................................................................ 1 3 模板方案选择与施工难点。 ............................................................................................ 1 3.1 施工现场情况 .............................................................................................................. 1 3.2 模板方案选择 .............................................................................................................. 1 3.3模板分项工程的难点 ................................................................................................... 2 4 施工准备 ............................................................................................................................ 2 4.1 技术准备 ...................................................................................................................... 2 4.2 机具准备 ...................................................................................................................... 3 4.3 材料准备 ...................................................................................................................... 3 4.4劳动力组织及职责分工 ............................................................................................... 3 5 主要施工方法 .................................................................................................................... 4 5.1 工艺流程 ...................................................................................................................... 4 5.2 脱模剂的选择及使用注意事项 .................................................................................. 4 5.3 箱涵底板模板设计 ...................................................................................................... 5 5.4 箱涵墙及拱顶模板设计及施工 .................................................................................. 6 5.5 洞口模板设计及施工 .................................................................................................. 7 5.6 模板的拆除 .................................................................................................................. 8 5.7 模板的存放、维护及修理 ........................................................................................ 8 5.8 冬期施工 ................................................................................................................... 10 6 质量保证措施及质量标准 .............................................................................................. 10 6.1 模板加工质量标准 .................................................................................................... 10 6.2 进场模板材料质量标准 .............................................................................................11 6.3 模板安装质量标准 .................................................................................................... 12
6.4 质量控制主要项目及质量通病的防治 .................................................................... 12 6.5 质量保证措施 ............................................................................................................ 13 7 安全文明施工、消防环保措施 ...................................................................................... 14 7.1 安全文明施工保证体系 ............................................................................................ 14 7.2 安全文明施工注意事项 ............................................................................................ 15 7.3 文明施工 .................................................................................................................... 16 7.4 消防环保措施 ............................................................................................................ 16 8 成品保护 .......................................................................................................................... 17
1 编制依据
图纸 名称 排水管涵改造工程施工图 混凝土结构工程施工质量验收规范 建筑工程大模板技术规程 规范、建筑施工高处作业安全技术规范 规程、建筑机械使用安全技术规程 标准 建筑工程冬期施工规程 建筑施工安全检查标准 混凝土结构施工图平面整体表示方法制图规则和构造详图 编号 GBJ50204-2002(2011版) JGJ74-2003 JGJ80-91 JGJ33-2001 JGJ104-2010 JGJ59-99 11G101-1 图集 其他 2 工程概况
排水箱涵为箱形混凝土结构,总长度约580m,断面外包尺寸约3.5m×4.35m(拱涵采用直墙拱顶断面,直墙高度1.7m,拱顶为直径2.5m半圆,拱涵顶板、侧墙厚0.50m,底板厚0.80/0.90m)。结构混凝土强度均采用C30,抗渗等级为P8,垫层采用C15混凝土;结构缝间距一般为15米,结构缝处设枕梁,结构缝处设橡胶止水带;排水箱涵内一侧设600mm宽检修道;箱涵埋深为7.6米~26.04米(按规划设计路面)。 3 模板方案选择与施工难点。 3.1 施工现场情况
1、本工程为管涵迁改工程,后期建筑群尚未开工,现场可用施工场地较大,为模板架料的堆放、运输及加工创造了有利条件。
3、本工程处于XX区,对于包括模板架料堆场、木工房等在内的材料堆场的设置提出了高效、安全卫生、环保、文明等方面的高要求。
2、本工程对现场消防要求高;现场预设消防蓄水池,作为消防水源,消防水池接出管径DN100,并做水表井。水表后接一路管径DN100,沿着箱涵边部进行布置,以保证可靠不间断的系统供水。
加工场地及模版堆放区配置便携式大水桶及“四四制”配置的灭火器材。 3.2 模板方案选择
根据图纸设计的构件尺寸及工程实际情况,本工程的模板选型及部分支撑体系做法
见表3.1所示。
表3.1 基础及主体结构模板选型
序号 1 2 3 4 部位 箱涵底板 箱涵墙体 肋柱 桩间挡板 模 板 15厚胶合板 15厚胶合板 15厚胶合板 15厚胶合板 支撑体系 主龙骨为φ48钢管,间距800mm;次龙骨50mm×100mm木方,间距200mm;钢管(木方)斜撑,间距1000mm; 主龙骨为φ48钢管,间距600mm;次龙骨φ25三级钢,间距1500mm;φ12对拉螺栓,间距600mm; 钢管,对拉螺杆,夹具。 次龙骨50mm×100mm木方,间距200mm;主龙骨为φ48钢管,间距500mm; 并设对拉螺栓;钢管斜撑固定。 3.3 模板分项工程的难点
1、箱涵顶部为拱形(异型),截面尺寸较为统一,模板工程的设计选型、加工配置、安装拆除是否科学、合理紧密关系到混凝土工程质量:
2、肋柱高度较高,一边紧挨边坡,模版的制作、安装是否能消除对边坡的施工质量隐患,为箱涵主体施工创造安全环境至关重要。
针对上述模板工程难点,我们将精心设计模板、精心施工,精心管理,确保模板工程质量,为确保混凝土工程质量创造条件,为确保结构工程质量打下坚实基础。 4 施工准备 4.1 技术准备
4.1.1技术准备 首先组织有关技术人员根据施工图纸进行模板方案编制和模板配制、用量统计,根据统计的模板数量和规格对模板厂家进行选材、定货。
4.1.2 测量准备 根据平面控制网线,放出箱涵平面控制轴线,再在边坡上放出肋柱、桩间挡板控制轴线,底板上放出墙体控制轴线。
4.1.3 熟悉图纸
施工前认真查阅图纸(边坡支护与箱涵主体)、方案、相关安全质量 规范,了解掌握模板的施工工艺,找出模板工程中的重点部位及异形部位、安全质量施工注意点等,作到异型模板配置及时、施工中重点突出。按图纸和项目部的施工进度计划合理安排材料、机具、人员进场施工。
4.1.4 其他
1、按施工方案和技术规程对操作者进行技术安全交底并下达具有可操作性、可实