编号:HBGJ-HCJY-C5.1-001
花城家园三期C5地块1-6#、9#楼及地下室工程
基础土方开挖及土钉支护施工方案
编制: 审核: 批准:
二0一四年三月二十日·····
·......
目 录
一、 工程概况 ....................................................................................................1 1.1 工程建筑概况 ........................................................................................... 1 1.2 工程地质条件 ........................................................................................... 1
1.2.1 地形、地貌 .......................................................................................1 1.2.2
场地地质条件 ..................................................................................2
1.3 周边施工条件 ........................................................................................... 5 1.4 编制依据 ................................................................................................... 5
1.4.1 业主提供资料: ...............................................................................5 1.4.2 国家及行业颁布的施工规范及规程: ............................................5 1.4.3 国家及武汉市颁布的评定标准 .......................................................6 1.4.4 施工现场及周围环境情况调查记录等。 .......................................6
1.5 工程施工目标 ........................................................................................... 6
1.5.1 质量目标............................................................................................6 1.5.2 安全目标............................................................................................6 1.5.3 文明施工目标 ...................................................................................6 1.5.4 环保目标............................................................................................6
二 施工部署及施工准备 ...................................................................................6 2.1 施工组织 ................................................................................................... 6
2.1.1 项目管理机构 ...................................................................................7
2.2 施工部署 ................................................................................................... 8
2.2.1 施工部署............................................................................................8 2.2.2 施工准备............................................................................................8
······
......
三 施工方案 ...................................................................................................... 11 3.1 土方开挖施工方案 ................................................................................. 11
3.1.1、土方开挖基本情况 ......................................................................... 11 3.1.2 土方开挖施工部署 ......................................................................... 11 3.1.3 土方开挖施工流程 ........................................................................ 12 3.1.4 土方开挖施工准备 ........................................................................ 12 3.1.5 土方开挖施工方案 ........................................................................ 13 3.1.6 质量保证措施 ................................................................................ 14 3.1.7 土方回填......................................................................................... 15 3.1.8 坑内排水......................................................................................... 15 3.1.9 坑边排水......................................................................................... 16
3.2 土钉喷锚施工 ......................................................................................... 16
3.2.1 工艺流程......................................................................................... 16 3.2.2 基坑放样......................................................................................... 17 3.2.3 坡面施工......................................................................................... 17 3.2.4 土钉施工......................................................................................... 17 3.2.5 绑扎、固定钢筋网 ........................................................................ 17 3.2.6 混凝土面层施工 ............................................................................ 17 3.2.7 技术质量要求 ................................................................................ 18 3.2.8 施工注意事项 ................................................................................ 18 3.2.9
工程质量保证措施 ....................................................................... 18
3.2.10 特殊情况的处理措施 .................................................................. 19 3.2.11 特殊情况应急处理: .................................................................. 20
······
......
3.3 基坑边坡变形监测 ................................................................................. 20
3.3.1 监测目的......................................................................................... 20 3.3.2 监测项目......................................................................................... 20 3.3.3 观测点设置 .................................................................................... 20 3.3.4 观测点制作 .................................................................................... 21 3.3.5 观测点保护 .................................................................................... 21 3.3.6 检测方案......................................................................................... 21 3.3.7 监测管理......................................................................................... 21 3.3.8 监测预警......................................................................................... 21
四 施工质量保证措施 .................................................................................... 22 4.1 工程质量保证措施 ................................................................................. 22
4.1.1 组织措施......................................................................................... 22 4.1.2 技术措施......................................................................................... 22 4.1.3 材料保证措施 ................................................................................ 23 4.1.4 设备保证措施 ................................................................................ 23
4.2 雨季施工措施 ......................................................................................... 23
4.2.1 雨季施工组织措施 ........................................................................ 23 4.2.2 施工技术措施 ................................................................................ 24 4.2.3 材料、机具准备 ............................................................................ 24 4.2.4 雨期防护......................................................................................... 24
5 安全文明施工保证措施 .............................................................................. 25 5.1 安全施工管理措施 ................................................................................. 25 5.2 安全施工技术措施 ................................................................................. 25
······
......
5.2.2 作业安全措施 ................................................................................ 25 5.2.3 临时用电防触电措施 .................................................................... 26 5.2.4 场内运输道路,人行道的布置 .................................................... 27 5.2.5 防火、防毒、防煤、防雷措施 .................................................... 27 5.2.6 施工设备使用安全要求: ............................................................ 27 5.2.7 安全施工要求: ............................................................................ 28
5.3 防止扰民施工保证措施 ......................................................................... 28 5.4 文明施工保证措施 ................................................................................. 29 六 施工应急预案............................................................................................. 30 6.1 目标与方针 ............................................................................................. 30 6.2 基坑施工的主要危险源 ......................................................................... 30 6.3 专项安全保证措施 ................................................................................. 30 6.4 施工应急预案 ......................................................................................... 30
6.4.1 组织机构......................................................................................... 30 6.4.2 事故上报......................................................................................... 31 6.4.3 组织机构职责 ................................................................................ 31 6.4.4 应急保障措施 ................................................................................ 32
七:基坑支护设计计算..................................................................................... 34 7.1、参数信息:............................................................................................... 34
7.1.1、基本参数: .................................................................................... 34 7.1.2、荷载参数: .................................................................................... 34 7.1.3、地质勘探数据如下:: ................................................................ 34 7.1.4、土钉墙布置数据: ........................................................................ 35
······