水库工程(
PPP模式)项目施工方案
年 月 日
1
目 录
目 录 .................................................................................................................................................................1 一、工程概况 .......................................................................................................................................................2
1.1概述 ........................................................................................................................................................2 1.2需要完成的工作内容 ............................................................................................................................2 二、编制依据和引用标准 ...................................................................................................................................2 三、施工布置 .......................................................................................................................................................2
3.1施工用电 ................................................................................................................................................2 3.2施工用水 ................................................................................................................................................3 3.3施工供风 ................................................................................................................................................3 3.4施工通风 ................................................................................................................................................3 3.5施工照明 ................................................................................................................................................3 3.6施工排水 ................................................................................................................................................3 3.7施工弃碴 ................................................................................................................................................3 四、施工程序及主要施工方法 ...........................................................................................................................4
4.1施工程序 ................................................................................................................................................4 4.2洞口开挖与支护施工方法 ....................................................................................................................4 4.3洞身开挖与支护施工方法 ....................................................................................................................4
4.3.1开挖钻爆施工工艺框图 ............................................................................................................5 4.3.2主要工序作业措施 ....................................................................................................................5 4.3.3隧洞开挖围岩爆破参数 ............................................................................................................7 4.3.4洞身支护 ....................................................................................................................................7
五、工期计划安排及工期保证措施 ...................................................................................................................9 六、质量保证措施 .............................................................................................................................................10 七、安全及文明施工保证措施 .........................................................................................................................10
7.1安全施工保证措施 ..............................................................................................................................10 7.2文明施工保证措施 .............................................................................................................................. 11 八、资源配置计划 .............................................................................................................................................13
8.1机械设备配置 ......................................................................................................................................13 8.2人员配备 ..............................................................................................................................................13
2
水库工程(PPP模式)项目放空(取水)洞施工Ⅰ标施工方案 一、工程概况
1.1概述
1、水库位于 ,主要任务是用于农业灌溉、城乡供水等。其中放空(取水)洞由导流洞改建而成,位于大坝右岸,洞内埋设直径800m取水钢管,满足下游灌溉、农村生活用水以及生态基流用水。
2、工程规模及内容:放空(取水)洞全长264m包括进水塔、洞身工程、出口消力池等工程,其中隧道长216m,城门洞型,开挖断面4.0mx6.0m。
1.2需要完成的工作内容
放空取水洞施工Ⅰ标:明挖、洞挖及支护施工。主要施工内容及工程量为:土石方开挖约4万m3,石方洞挖约6300m3,钢筋网24t,锚杆约1385根,喷砼约700m3等。具体见工程量清单。
二、编制依据和引用标准
1、水库工程放空取水洞招标设计图;
2、水库工程放空取水洞施工Ⅰ段招投标文件及合同文件; 3、《爆破安全规程》GB 6722—2011;
4、《水工建筑物地下开挖工程施工技术规范》DL/T5099-1999; 5、《水电水利工程喷锚支护施工规范》DL/T5181-2003); 6、《钢筋混凝土用热轧钢筋》GB1499; 7、《钢筋混凝土用热轧光面钢筋》GB/T13013; 8、《锚杆喷射混凝土支护技术规范》GB50086-2001。
三、施工布置
3.1施工用电
施工用电电源接线点从已有的高压线接出,在洞口附近设置630KVA变压器,然后用380电缆线接线引入洞内,另外在洞口布置1台150KW的柴油发电机,以确保因突发停电情况下洞内的通风、照明及支护的正常进行。
3
3.2施工用水
分别在进、出口附近进行打井取水,从已打好的水井抽至蓄水池。洞口分别建一座高位蓄水池,且每个洞口设置150JC18×12型水泵台向隧洞工作面供水。
3.3施工供风
放空取水洞开挖施工用风设备主要为:手风钻钻孔用风及喷混凝土用风,施工用风是在进、出口洞口各建设集中供风站,其中每个面钻爆高峰期手风钻按照6部计算,砼喷射机按照1台,每台手风钻用风量约为3m3/min,砼喷射机供风量按照9m/min计算,则用风量约为27m/min,所以供风站计划布设1台20m/min、1台10m3/min电动空压机和压力风灌,总供风量为30 m3/min,能够满足施工要求,供风线路采用Φ108钢管供风至施工工作面。
3
3
3
3.4施工通风
计划在进、出口各布置一台YBJM-2轴流风机,YBJM-2轴流风机通风量在14050~21670 m3/h,能够满足施工支洞和主洞将来的施工需要,通风风管采用400mm直径的塑料风管向洞内供风。
3.5施工照明
洞内照明线路采用50mm2的低压绝缘导线,沿边墙上部布置。洞内非作业地段采用220V防爆灯照明,每隔10~15m设置一盏。距离开挖工作面30m以内,改为36V安全电压照明,开挖、支护工作面照明采用低压投光灯具,另外,为防止施工中突然停电,施工人员配置12~24V手提作业灯作为应急照明。
3.6施工排水
洞内施工排水拟在所有靠近工作面设集水坑,布置1台水泵接排水管将洞内积水排到洞外,施工中约需2寸水管300m。
3.7施工弃碴
洞内开挖弃渣全部运出洞口后按照要求弃在指定的的渣场,分类有序堆存。
四、施工程序及主要施工方法
4.1施工程序
根据现场实际的地形地质条件,结合施工进度安排,开挖和支护同步进行,
4
施工总体程序和洞身开挖支护循环程序如分别如下:
1、施工总体程序:施工准备→洞口测量→洞口明挖及支护→洞身开挖→地质素描→洞内支护
2、明挖主要施工程序:岩面清理→初喷混凝土→锚杆施工→挂钢筋网→喷混凝土施工→下层开挖。
3、一般洞段开挖施工程序:测量放样→钻孔→装药→联网起爆→通风排烟→安全检查→出碴→安全处理→支护→掌子面清理→下一循环。
4、穿过断层破碎带等不良地质洞段开挖施工程序:测量放样→钻孔→装药→联网起爆→通风排烟→安全检查→安全处理→顶拱初喷混凝土→系统锚杆→出碴→钢支撑、顶棚、喷射混凝土(必要时)→掌子面清理→下一循环。
4.2洞口开挖与支护施工方法
洞口开挖首先采用反铲将洞脸表面覆盖层开挖掉,然后岩石部分采用YT28手风钻进行钻爆,洞口边坡分两级马道开挖,二级马道以上边坡开挖坡比按照1:0.75进行开挖,下部洞口部位边坡坡比按照1:0.5开挖,马道靠坡脚部位开挖排水沟,排水沟向山沟找坡排水。开挖土石方采用反铲配合ZL50装载机倒运至指定弃渣场。
洞脸从上向下开挖过程中,根据现场实际情况应及时进行支护处理,以防止雨水冲刷造成边坡失稳,洞脸支护根据地质情况采用C20喷射混凝土进行喷护,局部岩石完整性较差的部位打随机锚杆,并喷砼支护,喷砼厚度不小于10cm。
4.3洞身开挖与支护施工方法
根据本工程特点,洞内开挖应根据地质情况不同采用不同的开挖方法。放空洞开挖断面相对较小,采用全断面开挖方法,设计边线开挖采用光面爆破,出渣主要采用装载机出渣,洞身右侧布设风水电线路。
4.3.1开挖钻爆施工工艺框图
开挖施工工艺流程框图
开 挖 准 备 5 测 量 放 线 钻 孔