QTZ40B塔式起重机安装拆卸方案要点

天下 分享 时间: 加入收藏 我要投稿 点赞

QTZ40塔式起重机安装拆卸施工方案

编制单位:山东圣大建设集团有限公司编 制 人:审 核 人:编制时间:二

0一二年五月六日

QTZ400型塔式起重机安装拆卸方案

目 录

一、编制依据········································2 二、工程概况········································2 三、塔机选型········································2 四、施工现场情况····································3 五、塔机安装、拆卸施工方案··························3

1、 安装前的准备工作···························4 2、 安装步骤···································4 3、 塔身标准节的安装方法及步骤·················7 4、 调整各种安全装置···························8 5、 附着架的安装与使用·························11 6、 塔机的拆卸·································12 7、 塔机拆卸注意事项···························15 六、安全技术措······································16 七、拆装作业的岗位责任制和操作规程··················17 八、塔吊验收:·······································18

1

QTZ400型塔式起重机安装拆卸方案

一、 编制依据

现场平面布置图、施工图纸、塔机安装位置及周围环境、塔机使用说明书、《建筑机械技术试验规程》( JGJ34—86)和《起重机械安全规程》(GB6067—85)、塔机拆卸方法、地方有关规定等。

二、 工程概况

本工程为 ,位于 。 建筑层数为地下一层,地上一十七层;本工程功能分区为:设备用房及后勤辅助,位于地下一层;洗浴按摩区,位于地下一层至二层东侧;酒店大堂,位于一层;餐饮区,位于二至三层;会议区,位于四层;普通客房区,位于五至一十三层;套间客房区,位于一十四层;后勤管理办公室,位于一十五至一十七层;地上总高度为71.25m,总长度为60.40m,总宽度为36.20m; 建筑面积为25540m2,其中地下为2060 m2 ,地上为23480 m2;结构类型为,框架剪力墙结构;基础形式为桩基础;抗震设防类别为丙类,抗震设防烈度为六度;耐火等级为一级;设计规模为:客房共计207间;其中标准间179间,家庭间10间,两间套11间,三间套4间,豪华包间1间,残疾人客房2间。计划开工日

期为2012年4月26日,竣工日期为2013年10月31日。工期为553天。 三、 塔机选型:

根据本工程建筑高度及施工现场面积建筑物外形等选QTZ40(自升式)塔机,由山东圣大建设集团有限公司起重机械安装队安拆,.塔机立于主楼南侧,详细位置见施工现场布置图(附后)。 四、现场施工情况

经堪察,施工现场空中及地下均无高压线路、障碍物,现场

2

QTZ40B塔式起重机安装拆卸方案要点

QTZ40塔式起重机安装拆卸施工方案编制单位:山东圣大建设集团有限公司编制人:审核人:编制时间:二0一二年五月六日<