新建杭州至长沙铁路客运专线(江西段)
站前工程HKJX-5标
绿色通道试验施工方案
编 制: 审 核: 审 批:
中铁十六局沪昆客专江西段站前工程 HKJX-5标项目经理部 二○一三年二月 沪昆客专江西段HKJX-5标绿色通道首件工程施工方案 目 录
1.编制依据 ····································································································· 1 2.工程概况 ····································································································· 2 2.1.试验段选取 ······················································································· 2 2.2. 绿色通道施作试验段工程概况 ······················································ 2 3. 绿色通道施作施工组织安排 ···································································· 5 3.1. 组织机构及人员组成 ······································································ 5 3.2. 主要设备配置 ················································································· 6 3.3. 施工计划 ························································································· 7 4. 绿色通道施工方案 ··················································································· 7 4.1. 绿色通道绿化防护样式 ·································································· 7 4.2. 施工方案及工艺 ··········································································· 17 5. 种植基本要求 ························································································· 29 5.1. 一般原则 ······················································································· 29 5.2.植物种植安全性原则 ······································································ 30 5.3.苗木的种植修剪及植后养护管理 ·················································· 30 6. 绿化施工质量控制 ················································································· 31 6.1.施工过程技术控制 ·········································································· 31
沪昆客专江西段HKJX-5标绿色通道首件工程施工方案 6.2.种植及养护技术控制 ······································································ 32 7. 安全、文明施工措施及环保措施 ·························································· 34 7.1. 安全施工措施 ··············································································· 34 7.2.文明施工措施 ················································································· 38 7.3.环境保护 ························································································· 39
沪昆客专江西段HKJX-5标绿色通道首件工程施工方案 杭长客专江西段HKJX-5标 绿色通道试验段施工方案
1.编制依据
1)《铁道部工管中心关于加强铁路绿色通道工程建设管理的通知》(工管线路函[2012]396号);
2)《铁路路基边坡绿色防护技术暂行规定》(建技[2003]7号); 3)《铁路绿色通道设计暂行规定》(铁建设函[2004]551号); 4)《铁路绿色通道建设实施指导意见》(铁建设函[2007]472号); 5)《关于调整在建及新建铁路绿色通道设计有关问题的通知》(铁鉴函[2007]544号);
6)《关于进一步做好铁路绿色通道建设工作的通知》(建技[2008]27号);
7)《铁路工程施工组织设计指南》(铁建设[2009]226号); 8)铁四院《新建铁路杭州至长沙铁路客运专线江西省境内绿色通道设计方案》;
9)《杭长客专路基工程设计详图集》及铁四院首次设计技术交底资料;
10)新建铁路杭州至长沙铁路客运专线施工图《区间路基绿色通道设计大样图》;
11)《杭长客专江西段绿色通道工程建设指导意见》(沪昆赣工[2012]70号);
1
沪昆客专江西段HKJX-5标绿色通道首件工程施工方案 12)《沪昆客专江西公司关于下发杭长客专江西段绿色通道专项工程指导性施组的通知》(沪昆赣工[2013]4号);
13)新建铁路杭州至长沙铁路客运专线施工图《路基设计图》; 14)国家和铁道部现行施工技术规范、规程及标准。 2.工程概况 2.1.试验段选取
新建铁路杭州至长沙客运专线站前工程HKJX-5标段,起止里程为DK569+839.17~DK638+468.75,线路全长68.630km,其中正线路基长23.005km/31段,桥梁全长45.625km/30座。本标段绿色防护主要工程量有:喷播植草6798m2、喷混植生3720m2、栽植乔木30.98千株、栽植灌木597.78千株、客土种植11.7万m2。
为指导本管段内绿化防护施工,起到绿化防护施工示范作用,本管段选定DK590+580.83~DK592+151.29段路基作为绿色通道试验段。本段路基全长1570.46m,其中填方842.20m,挖方728.26m,最大填高 8.073m,最大挖方高13.995m。
2.2. 绿色通道施作试验段工程概况
⑴地形地貌:
路基位于低缓岗地及坳谷区,岗地地形波状起伏,地面坡度12~17°,植被较发育,多种植为树木及杂草丛生,坳谷区地势平坦、开阔,自然坡度3~7°,辟为水田,交通较便利。
⑵地层岩性及工程地质条件:
2