CONSTRUCTION PROCEDURE OF SUBSTATION AND DISTRIBUTION DEVICES变电所及配电设备施工程序 Plant: PP+HDPE Contractor: TISA Subcontractor: CP6CC of CNPC REF. NO: 编号 NH-HDPE+PP-WPR-220 REV: B Page: 1of 11 Client: CSPC

CONTENTS

1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0

Scopes 范围

Reference documents 参考文献

Inspection and storage of equipment and materials 设备、材料的检验和储存 Installation of Switchgear 开关柜安装

The installation of electrical units of high and low voltage 高低压电气开关安装 The installation of transformer 变压器安装 The installation of the bus 母线安装 Connection of Cables 电缆连接

The installation of direct current system and UPS 直流系统、UPS安装

10.0 Test 测试

11.0 Construction quality records and inspection report 施工质量记录和检查报告 12.0 Revision 修订

CONSTRUCTION PROCEDURE OF SUBSTATION AND DISTRIBUTION DEVICES变电所及配电设备施工程序 Plant: PP+HDPE Contractor: TISA Subcontractor: CP6CC of CNPC REF. NO: 编号 NH-HDPE+PP-WPR-220 REV: B Page: 2of 11 Client: CSPC 1.0

Scope: 范围

This procedure applies to electrical engineering installation of substation and distribution devices of the electrical engineering for the HDPE+PP Plant on the CSPC Nanhai Petrochemicals Project, in China.

本程序文件适用于南海石化项目HDPE+PP装置电气工程变电站和配电装置工程安装。

2.0 2.1

Reference Document: 参考文件

The effectual edition construction drawings approved by CONTRACTOR 承包商提供的有效版本的施工图

2.2

The standard specifications of project:

3163NNSC201 Electrical Works Specification 电气工作标准

3163NNSC204 Electrical Works—Site Inspection Plan电气工作现场检查计划 3163nnwr201 Electrical Works Requisition电气工作申请 TM780.1/94E Testing of Electrical Installation电气测试

SP-8530-0000-0001 Electrical Design General Specification电气设计一般规范 DEP 33.64.10.10 Electrical Engineering Guidelines电气工程指南 TM775_1_97E Erection of Electrical Installations. 电气装置安装

TM775_4_97E Storage of electrical materials before installation 电气 材料 的

储藏

SP-8530-0000-0006 Rev 01 Substation Design Specification.变电所设计规范 SP-8530-0000-0010 Rev 00 Technical Specification for Neutral Earthing Device 中

性接地设备技术规范

SP-8530-0000-0018 EMC Installation Guidelines EMC安装指南 SP-8530-0000-0022 Rev 00 Electrical Design Specification for EHV Switchgear

EHV开关柜电气设计规范

SP-8531-0000-0006 Rev A Substation Design Specification变电所设计规范

CONSTRUCTION PROCEDURE OF SUBSTATION AND DISTRIBUTION DEVICES变电所及配电设备施工程序 Plant: PP+HDPE Contractor: TISA Subcontractor: CP6CC of CNPC REF. NO: 编号 NH-HDPE+PP-WPR-220 REV: B Page: 3of 11 Client: CSPC SP-8531-0000-0007 Rev A Electrical Design Specification for Package Equipment设

备包的电气设计规范

DEP 63.10.08.11- CSPC Field Commissioning and Maintenance of Elect Instaland

Equip.电气设备运行和维护

TM761_31_94E Totally Enclosed Elect Equip Testing电气设备完全封闭

试验

DEP 33.65.40.31-CSPC Power Transformers电力变压器

DEP 33.65.50.31-CSPC Static DC Uninterrupted Power Supply静态直流不间断

电源

DEP 33.65.50.32-CSPC Static AC uninterrupted Power Supply Unit静态交流不间

断电源

DEP 33.66.05.33-CSPC Electrical Variable Speed Drive Systems电气 调速系统 DEP 33.67.01.31-CSPC Low-Voltage Switchgear and Controlgear 低压的开关柜

和控制盘

DEP 33.67.51.31-CSPC High-Voltage Switchgear and Controlgear高压的开关柜

和控制盘

24884-100-3DR-E12F-00001 Electrical Systems 电气系统

3.0

Test And Storage Of Electrical Equipment And Materials: 设备和材料的检验和存放

3.1

All materials received at site shall be handled in accordance with the specification requirement of NH-HDPE+PP-PR-112 PROCEDURE FOR LOADING UNLOADING PUTTING OUT MATERIAL .

3.2 3.3

现场接收的材料管理应按NH-HDPE+PP-PR-112 材料装卸及发放程序处置。 The equipment and materials delivered to site shall have the factory certificates and necessary manufacturer’s technical documents. They shall be examined to make sure they are as per the purchase order's requirements. Perform visual inspection to defect any defects such as damage, corrosion or deformation.

CONSTRUCTION PROCEDURE OF SUBSTATION AND DISTRIBUTION DEVICES变电所及配电设备施工程序 Plant: PP+HDPE Contractor: TISA Subcontractor: CP6CC of CNPC REF. NO: 编号 NH-HDPE+PP-WPR-220 REV: B Page: 4of 11 Client: CSPC 3.4 送交现场的设备均应有出厂合格证和必要的厂家技术文件,检查是否符合订购要求,外观检查是否有损坏、锈蚀、变形等缺陷。

3.5 Record and check name plate data. Check the components of switchgears and panels and the accessories to ensure they are complete and in compliance with the specifications of the orders.

3.6 3.7

记录并检查铭牌,检查开关柜元件和附件是否齐全,并应符合定单要求。 The instruments and apparatus of all the panels shall be free from mechanical damage, scratches and other faults.

表盘的仪表、仪器等应无机械损伤,刮痕和其它缺陷。

3.8 The equipment and materials shall be properly stored in dry and clean place to avoid dust, moisture and corrosion.

设备材料应妥善存放在干燥干净的地方,以防灰、防潮、防腐。

4.0 4.1

Installation of Switchgear: 开关柜安装 Switchgear shall be installed on above steel frame. 开关柜应安装在钢架上

4.1.1 The switchgear shall be properly installed and bolted to location in switchgear room in accordance with switchgear installation layout.

按开关柜安装布置图将开关柜安装在开关室内合适的位置,并用螺栓固定。

4.1.2 While installing steel frame foundation, the horizontality, perpendicularity and parallelism between two pieces of shape steel shall be within the scope of the drawing specified.

基础型钢在安装时,其水平度,垂直度和两型钢间的平行度均应在图纸规定范围内。

4.1.3 The steel frame foundation shall be earthed reliably as per the drawing’s requirement. 基础型钢必须按图纸要求可靠接地。

4.2 The installation of switchgear: 开关柜安装

4.2.1 Before the installation of switchgear, check the equipment by opening package against the construction details and progress status with the QC personnel write a record based on the result of inspection.

CONSTRUCTION PROCEDURE OF SUBSTATION AND DISTRIBUTION DEVICES变电所及配电设备施工程序 Plant: PP+HDPE Contractor: TISA Subcontractor: CP6CC of CNPC REF. NO: 编号 NH-HDPE+PP-WPR-220 REV: B Page: 5of 11 Client: CSPC 开关柜在安装前按施工图及进度情况会同QC部人员进行开箱检查,并填写有关记录。

4.2.2

The switchgear shall be fixed to the steel frame by bolts after its alignment. Check for alignment, levelness and tightness of foundation bolts.

开关柜找正后用螺栓固定在基础型钢上,检查基础螺栓的对中、垂直度、水平度及紧固度。

4.2.3

Switchgear shall be grounded reliably in accordance with construction details. Inspection equipment earthing system and measure the grounding resistance. 开关柜应按施工图要求做好可靠接地,同时检查接地系统和测量接地电阻。

4.2.4

After installation, check the mechanical interlock and electrical interlock to ensure they are exact and check the contacts to see if they are tight.

安装后,检查开关柜的机械联锁、电气联锁是否准确,接触是否紧密。

4.2.5

Check breakers with track and distribution units with drawer to check the alignment of drawout mechanism and see if they are movable free, units of same type can be interchangeable.

检查带轨道断路器和抽屉式配电单元,检查拉出机构是否应灵活,相同型号的单元是否能互换。

4.2.6

Panel body and interior devices shall be connected firmly with all structural members, check the fuses, CT&PT, indicators and relay to ensure they are all in compliance with design requirements.

柜体及柜内设备与各结构构件连接应牢固,检查柜内熔断器、互感器、仪表用变压器、指示器和继电器应符合设计要求。

5.0

The Installation Of Electrical Switchs Of High And Low Voltage: 高低压电气开关安装

5.1

If breakers and switchgears are packed in separate cases, check the breakers and controlling mechanism when received to ensure the parts are complete, free from mechanical damage or corrosion, and insulation parts shall not be found deformation or damped.

若断路器与开关柜分箱包装,到现场后应检查断路器及操动机构零部件齐全,无

NH-HDPE+PP-WPR-220 变电站与配电装置安装程序 B 

CONSTRUCTIONPROCEDUREOFSUBSTATIONANDDISTRIBUTIONDEVICES变电所及配电设备施工程序Plant:PP+HDPEContractor:TISASubcontractor:CP6CCofCNPCREF.NO:编号NH-HDPE+PP-WPR-220REV:BPage:1of11Clien
推荐度:
点击下载文档文档为doc格式
5gm8v9bmlp1od1e2lms547le14lopx00wjd
领取福利

微信扫码领取福利

微信扫码分享