DLGT01 钢管杆、铁塔组立安装作业指导书

第8部分:配网工程

钢管杆、铁塔组立安装作业指导书

编码:DLGT-01

1

中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程

目 次

1 适用范围··························································································································································3 2 编写依据··························································································································································3 3 作业流程图·······················································································································································3 4 安全风险辨析与预控·······································································································································3 5 作业准备··························································································································································4 6 作业方法··························································································································································5 7 质量控制措施及检验标准·······························································································································6

2

DLGT-01钢管杆、铁塔组立安装作业指导书

1 适用范围 1.1 电压等级

35kV及以下配网工程。 1.2 电气类别钢管杆、铁塔组立工程

的安装。

2 编写依据

表2 编

序号

写 依 据

引用资料名称 1 GB 50173—1992《电气装置安装工程35kV及以下架空电力线路施工及验收规范》 GB 50233—2005《110~500kV 架空送电线路施工及验收规范》 DL 5009.2—2004《电力建设安全工作规程第2部分:架空电力线路》 Q/CSG 11105—2008《南方电网工程施工工艺控制规范》 《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》 2 3 4 5

3 作业流程图

图3 作业流程图

4 安全风险辨析与预控

4.1 4.2

钢管杆、铁塔组立安装前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安 按《指南》中与钢管杆、铁塔组立安装相关联的《电网建设安全施工作业票》(编码:

全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。 DLGT-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。

3

中国南方电网有限责任公司电网建设施工作业指导书第8部分:配网工程

4.3 4.4

施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须

表4.1

作业指导书安全基准风险指南

风险等级 中等风险 中等风险 人员负责将安全措施落实到各作业任务和步骤中。 重新办理作业票,在工作完成后上交项目部保存备查。

序号 1 2 危害名称 施工区域安全围蔽措施不足 设备材料顺斜坡堆放 风险种类 打击、坠落摔绊 打击碰撞 夹伤碰撞打击 打击、碰撞夹伤 打击碰撞 风险控制措施 施工区域必须按规范做好安全围蔽及警示措施,晚上应设置警标灯 设备材料不得顺斜坡堆放,加支垫或用绳索锚固塔材,组装时应防止塔材滑动 1. 排杆前应平整场地或支垫坚实; 2. 用绳索或拉线锚固电杆 3 山坡排杆没有平整场地或支垫措施不当 杆、塔连接螺栓连接不牢固 没按安全系数选取钢丝绳套及卸扣 中等风险 4 5 中等风险 中等风险 1. 检查杆、塔连接情况,按规范扭矩紧固螺栓; 2. 铁塔附材螺栓要露扣并用铁丝绑扎牢固 按吊装重量选取安全系数相匹配的钢丝绳套及卸扣,卸扣U形环变形或销子螺纹损坏不得使用 1. 动火作业要办理动火作业票,严格执行气、电焊作业操作规程; 2. 清除动火区域易燃易爆物品和杂物 1. 作业人员应正确使用劳动防护用品; 2. 严格执行气、电焊作业操作规程; 3. 焊工必须持证上岗 1. 工作前应检查线缆及接线点是否良好; 2. 焊机二次线路及外壳必须接地良好; 3. 焊把不得破损,绝缘必须良好; 4. 雨天不要在露天烧焊,在潮湿地方电焊作 业,应站在绝缘垫上 1. 乙炔瓶要垂直放置,正确安装防回火装置; 2. 现场应配备足够灭火器材; 3. 氧气瓶与乙炔瓶距离不得小于8m,距明火 距离不得小于10m 1. 氧气管、乙炔管有龟裂时应禁止使用; 2. 作业现场应配备足够灭火器材 1. 动火作业要办理动火作业票; 2. 现场配备合格有效、数量足够且型号与现场 物质相对应的消防器材 1. 电源箱按规定安装漏电保护开关; 2. 所有电器设备的金属外壳接地线牢固可靠; 3. 不得将电线直接钩挂在开关上、直接插入插 座内使用或采用铜丝代替熔丝使用; 4. 开关、插座、设备外壳不得有明显破损以及 设备带电金属不得外露; 5. 施工现场临时电源线不得乱拉乱接,应使用 软橡胶电缆线; 6. 电焊机电源应加装开关才能接入使用 1. 避开炎热高峰时段作业,现场配置太阳伞或风扇,配备足够的清凉饮料和急救药物; 2. 对员工进行紧急救护法培训 6 没有清除动火区域易燃易爆物品和杂物 气、电焊作业人员不正确使用劳动防护用品 灼(烫)伤爆炸 中等风险 7 烫伤 中等风险 8 绝缘降低的电焊设备 触电灼 (烫)伤 中等风险 9 乙炔瓶没有安装防回火灼(烫)伤装置,氧气瓶明火距离不足 爆炸窒息 有缺陷的氧气、乙炔管 灼(烫)伤爆炸、窒息 中等风险 10 中等风险 11 动火作业现场没有配备消防器材 灼(烫)伤 爆炸窒息 中等风险 12 施工用电不规范 触电灼 (烫)伤设 备烧损 中等风险 13 防暑降温措施不足 中暑 高风险 4

DLGT-01钢管杆、铁塔组立安装作业指导书

序号 危害名称 起重设备安全装置失效* 风险种类 打击坠落 风险等级 中等风险 风险控制措施 1. 起重设备应持有效检验合格证; 2. 安全警示装置应齐全有效 14 5 作业准备

5.1 作业前施工条件

表5.1 作业前施工条件

序号 1 2 3 4 5 项目 任务单 图纸 预算材料表 施工方案 相关证照 内 容 确认人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 本工序施工负责人 说明 经审批 经审批 经审批 经审批 有效 根据工程项目实际设置内容(包含本项工作) 设计图纸、设备变更单 主、辅材清单 施工组织、安全技术交底(项目级) 根据需要办理进入工作场所的相关手续、证件 6 确认上一道工序检查合格 (1)钢管杆基础坑深度允许误差为50mm,+100mm;双 杆基坑中心偏差不应超过±30mm。 (2)铁塔基础:分解组立铁塔混凝土抗压强度应达到设 计强度的70%;整体立塔基础混凝土强度应达到100%, 本工序施工负责人 当采取有效防止基础承受水平推力的措施时,混凝土的抗 压强度应不低于设计强度的70%;装配式预制基础的底 座与立柱连接的螺栓、铁件及找平用的垫铁,应采取有效 的防锈措施 合格

5.2 人员、主要工器具及仪器仪表配置

表5.2 人员、主要工器具及仪器仪表配置

序号 项目 内 施工阶段 钢管杆、铁塔组装 吊装 现场材料整理 建议工作人数 技术工人5+装 卸工10 容 现场施工负责人 说 现场施工质 安员 明 1 人员配置 钢管杆、铁塔技术工人5+辅 助工10 技术工人2+辅助工5 1 1 技术岗位必须持有与作业工种相应、有效的上岗证,辅助工不得从事电气设备安装等专业工作 2 施工内容相对应的材料 钢管杆组件、铁塔组件、角铁金具、配套螺栓 检查设备材料符合设计要求: ①?主、附件清单齐全;②??钢管 杆构件不应有明显凹坑、扭曲; ③?圆钢、角钢不得有洼陷、凹痕、 裂缝? 3 工具:管子钳、电(气)焊工具、手锤、撬棍、铁铲、铁 施工内容相 锹、铁镐、滚杠、活络扳手、套筒扳手、钢丝绳、钢丝绳套、对应的器根据现场情况使用器具符合相卸扣、麻绳、扭力扳手、梅花扳手、圆木、梯子、相应吨位滑具、机械及关要求? 车及链条葫芦等。 工器具仪表 机械:相应起重等级的吊车? 完成开工程序 工作负责人向项目负责人报开工,并由项目负责人完成向? 监理单位开工报审手续 4

5