目 录
一、工程概况 .......................................................................................................................... 1 二、编制依据 .......................................................................................................................... 3 三、施工工艺 .......................................................................................................................... 3 四、施工准备 .......................................................................................................................... 4 五、施工方法 .......................................................................................................................... 5 六、机构及劳动力组织 ......................................................................................................14 七、施工平面布置 ...............................................................................................................17 八、质量保证体系及措施 ..................................................................................................18 九、安全保证体系及措施 ..................................................................................................19
一、工程概况
1.1工程概述
XX钢四烧360m2烧结机工程中,二次混合机系统设备总重约284.7t。二次混合机筒体重量约142t,分散式底座最重约12.627t。主要设备重量及数量如下:
345678910111213141516171819排 料 端 托 辊 罩排 料 端 托 辊筒 体 装 配齿 轮 罩给 料 端 托 辊 罩给 料 端 托 辊喷 水 装 置给 料 端 漏 斗给 料 端 漏 斗 支 架废 油 收 集 箱传 动 装 置落 料 收 集 箱喷 蒸 汽 装 置齿 轮 检 修 平 台废 油 收 集 箱筒 体 内 保 护 支 架电 动 干 油 及 喷 油 润 滑 装 置0.4370.061t4.853t2.2536.517t35.216t141.23t3.116t3.316t31.753t1.4t1.164t2.072t0.43t36.3t0.101t11111111141111111 1.2基本设计参数
1.3工程特点
① 设备安装前期的准备工作时间紧张,工作量巨大。
② 设备几何尺寸大,且运输筒体的拖车长达45m左右,转弯半径35m,对进场弯角处道路要求很高。
③ 设备的单体重量达142t,由于无法协调到汽车吊,只能用“土法”对二混筒体进行卸车、移动就位,施工难度大,危险系数高。