一 开工前的准备工作 二 地基基础工程施工 2.1土方开挖·································································01 2.2基土钎探·································································01 2.3验槽·····································································02 2.4地基处理·································································02 2.5垫层·····································································03 2.6钢筋工程·································································04 2.7模板工程··································································07 2.8混凝土基础································································08 2.9砖基础····································································11 2.10防潮层···································································11 2.11回填土···································································12 三 主体工程 3.1砌砖工程·································································13 3.2混凝土多孔砖工程··························································13 3.3钢筋工程·································································14 3.4模板工程·································································14 3.5砼工程···································································15 3.6预置空心楼板工程·························································16 四 装饰装修 4.1抹灰工程·································································18 4.2地暖工程·································································19 4.3外墙保温工程·····························································20 4.4室内防水工程······························································22 4.5铝塑门窗安装······························································23 4.6面砖镶贴··································································24 4.7内、外墙涂料粉刷工程·····················································25 五 屋面工程 安装篇
一 基础电气工程·····························································27 二 基础给排水工程···························································27 三 主体电气工程·····························································27 四 主体给排水工程···························································28 五 装修电气工程·····························································28 六 装修给排水工程···························································29 其它········································································32 建筑工程材料检验取样标准····················································33 建筑工程施工质量验收统一标准················································37 规范标准基本用词说明························································41 建筑工程资料管理基本要求····················································42
一、开工前的准备工作
一、开工前的准备工作:
1.编制监理规划、监理细则、旁站方案、安全监理规划、安全监理细则、安全旁站方案。 2.审查施工单位施工组织设计、技术交底、工程管理人员上岗证。
3.应搜集的资料:施工许可证;规划许可证;施工单位资质、安全生产许可证、现场管理人员名单。
4.熟悉高程控制点及轴线控制桩。 5.熟悉图纸及现场情况.
6.主持召开第一次监理会议,需明确内容:监理人员职责及分工;监理管理工作的一些要求和规定;例会召开的时间、地点、主要参加人员。
二、地基基础工程施工
1.土方开挖
1.一般规定
1.1土方开挖时,应防止附近已有建筑物或构筑物、道路、管线等发生下沉和变形。应与设计单位或者建设单位协商采取保护措施,并在施工中进行沉降和位移观测。当土方工程挖方较深时,应采取措施,防止基坑底部土的隆起并避免危害周边环境。
1.2土方不应堆积在基坑边缘。材料堆放应距坑沿1米以上的距离,堆土高度不超过1.5米。 2.监理要点
2.1基槽开挖前,楼体放线必须经规划部门验收合格。
2.2严禁超挖,如果超挖,超深部分的处理应由设计单位确定方案,施工单位不得擅自填埋。 2.3冬季开挖后,如基础垫层不能紧跟施工,应将基坑(槽)覆盖,防止基土冻结。 2.4当开挖深度超过3米或虽开挖深度没超过3米但地质条件和周边环境复杂的,应采取基坑支护措施。
2.5采用机械施工时,只能挖至设计高程以上30cm,以下用人工挖至设计高程。
2.基土钎探
1.一般规定
1.1为探明地基在一定深度内是否存在坟坑、古井、古河道、人防工程等异常和土质分部不均情况,对地基进行钎探。
1.2钎眼距离当设计没有规定,且满堂开挖时,其距离不大于1.5米,呈梅花型布置,钎探
深度不得小于1.8米。
1.3钎眼布置应和钎眼布置图相符。钎探数据应真实有效,填写清晰,钎眼标识应清晰,便于查找。钎点位置用白灰方格线控制,探孔离槽边0.2米左右。
2.监理要点
2.1检查钎眼深度。用2米长钢筋,检查实际钎探深度。 2.2灌砂。验完槽后,应及时用细砂灌钎眼。
3.验 槽
验槽由建设单位组织,设计、勘察、施工、监理、质检站参加。验槽意见以勘察和设计为主。验槽意见必须形成书面文件,并有各责任主体签字。没有书面验槽文件,不得对地基进行处理。
4.地基处理
1.灰土地基. 1.1一般规定:
1.1.1灰土应拌合均匀,颜色一致,并保持一定的湿度,加水量宜为拌合料总重量的16 %。 1.1.2灰土分段施工时,上下两层灰土的接槎距离不得小于500mm。当灰土垫层标高不同时,
应作成阶梯形。接槎时应垂直切齐。接缝不要留在荷载较大的部位。
1.1.3灰土最上一层完成后,应拉线或用靠尺检查标高和平整度,超高处用铁锹铲平;低洼
处应及时补打灰土。
1.1.4宜优先选用黏土、粉质黏土或粉土,不得含有有机杂物,使用前应先过筛,其粒径不
大于15mm。
1.1.5石灰应用块灰,使用前应充分熟化过筛,不得含有粒径大于5mm 的生石灰块,也不得
含有过多的水分。
1.1.6当灰土厚度小于等于20cm时,可采用小型机械搅拌(30或50拖拉机);当灰土厚度
大于20cm小于等于30cm时,需用大型灰土拌和机搅拌,也可用小型机械分两层搅拌。当厚度超过30cm时,应分层搅拌。 1.2监理要点:
1.2.1控制白灰用量。根据铺设厚度计算出用灰量,然后和施工单位的实际进灰量进行比较。
3:7灰土每立方白灰含量0.21立方(0.245T),2:8灰土每立方白灰含量0.14立方。 1.2.2灰土拌合后,应保持一定灰土的湿度,应以手握成团,两指轻捏即碎为宜。 1.2.3灰土应连续进行,尽快完成,施工中应有防雨排水措施,刚打完或尚未夯实的灰土,
如遭受雨淋浸泡,应将积水及松软灰土除去,并补填夯实;受浸湿的灰土,应晾干后再夯打密实。
1.2.4灰土垫层不宜冬期施工,当施工时必须采取措施,并不得在基土受冻的状态下铺设灰
土,土料不得含有冻块,应覆盖保温,当日拌合的灰土,应当日铺完夯完,夯完的灰土表面应用塑料薄膜和草袋覆盖保温。 2.砂和砂石地基
2.1一般规定:
2.1.1铺筑砂(或砂石)的厚度,一般为150-200mm,不宜超过300mm,分层厚度可用样桩
控制。视不同条件,可选用夯实或压实的方法。夯实可采用平板振动器,压实可采用6—10吨的压路机。
2.1.2砂和砂石宜铺设在同一标高的基土上,如深度不同时,基土底面应挖成踏步或斜坡形,
接槎处应注意压(夯)实。施工应按先深后浅的顺序进行。
2.1.3分段施工时,接槎处应作成斜坡,每层接槎处的水平距离应错开0.5~1.cm,并充分压(夯)实。
2.1.4.铺筑级配砂在夯实碾压前,应根据其干湿程度和气候条件,适当洒水湿润,以保持砂
的最佳含水量,一般为8 %~12 %。
2.1.5采用砂石处理时,应按配比在搅拌机里搅拌,不得在现场随用随调。
2.1.6施工时应分层找平,夯压密实,最后一层压(夯)完成后,表面应拉线找平,并且要
符合设计规定的标高。 2.2 监理要点:
2.2.1垫层的铺设,应待其下一层检验合格后方可施工上一层。砂石配比应均匀,不得出现
石子或砂子集中现象。振捣必须密实,不得有漏振现象。
2.2.2)砂和砂石不得含有草根等有机杂质;砂应采用中砂;石子最大粒径不得大于垫层厚度
的2/3。
2.2.3砂石施工应连续进行,尽快完成,施工中应有防雨排水措施,刚铺筑完尚未夯实的砂
石,如遭受雨淋浸泡,应将积水排走,晾干后再夯打密实。
2.2.4不得在基土受冻的状态下铺设砂石,砂中不得含有冻块,夯完的砂石表面应用塑料薄
膜或草袋覆盖保温。砂石垫层冬期不宜施工。 3. 其他。
3.1 地基处理完成以后,必须经过监理验收,才能进行下一道工序,有必要时可请设计人
员参加验收。
3.2 桩基、符合地基必须有有资质的检测部门出具的检测文件。
5.垫层
1. 一般规定
1.1 垫层施工前,主要材料应有试验室出具的检测报告。水泥应有3d或7d的报告。 1.2 施工单位的计量器具应配备齐全,且准确有效。搅拌机旁应设置配合比标牌。试验室
配合比应根据实际砂、石的含水率调整成施工配合比。砂石料场必须硬化。 1.3 槽底标高应符合设计要求,用水准仪进行测量。 1.4 垫层表面应平整,无露石现象.。 2. 监理要点: