2.编制依据················································1 3.适应范围················································1 4.工程概况················································1 4.1设计概况·············································1 4.2工程地质及水文概况···································2 5.确定安全措施············································2 6.具体安全防护措施········································2 6.1承台基坑安全防护措施·································3 6.1.1机械设备安排表 ··································3 6.1.2基坑开挖前的计算·································4 6.1.3 基坑开挖安全防护·································5 6.1.4 基坑施工的其它安全防护···························7 6.2 墩柱施工安全防护措施································7 6.2.1 脚手架安全防护措施·······························7 6.2.2 墩柱模板施工安全措施·····························9 6.2.3 高空作业安全防护措施····························11 6.3 连续梁施工安全防护措施·····························13 6.3.1挂篮拼装防护····································13 6.3.2已浇梁段防护····································13 6.3.3挂篮施工防坠落··································14 6.3.4 挂篮施工的其它安全防护··························14
石武客专河南段项目部四分部 跨石油管道连续梁专项安全施工方案
1 编制说明
为预防连续梁施工现场意外事故的发生,保证连续梁施工安全,特编制此专项施工方案,以指导现场安全施工。
2 编制依据
《客运专线铁路桥涵工程施工质量验收暂行标准》 《客运专线铁路桥涵工程施工技术指南》 《铁路混凝土工程施工质量验收补充标准》 《石武客专施工图设计文件》 3 适用范围
本方案适用于中铁十九局集团有限公司石武客专河南段项目部四分部史凹跨济东高速公路特大桥的跨石油管道连续梁部分,具体墩号为38#至41#。
4 工程概况 4.1 设计概况
四分部史凹跨济东高速公路特大桥的跨石油管道连续梁部分起
讫里程分别为DK594+532.44~DK594+646.04,为预应力现浇连续梁。
承台都为矩形两层台,其中38#、41#主墩承台尺寸为12.5m×8.1m×2.5m,加台尺寸为8.2m×4.6m×1.5m;39#、40#主墩承台尺寸为14.6m×10.6m×3m,加台尺寸为10.1m×6.1m×2m。
38#~41#承台基坑深分别为4.703m、5.879m、5.609m、4.890m。39#、40#两个主墩的承台基坑采用四周打槽钢进行防护的方式,而38#、41#两个主墩的承台基坑则采用平行路线方向的两边打槽钢,另外两边放坡进行防护的方式。
墩柱采用双线圆端型桥墩,墩高在14~14.25m,全部属高空作业。桥墩采用搭设脚手架进行施工。
梁体为单箱单室、斜腹板、变高度、变截面结构。箱梁顶宽12.0m,箱梁底宽5.0~5.5m。连续梁全长113.5m,计算跨度为(32+48+32)m,中支点处梁高4.05m,跨中8.4m直线段,边跨12.95m直线段,梁高3.05m,梁底下缘按二次抛物线变化,边支座中心线至梁端0.75m。采用悬臂挂篮施工的方法。
4.2 工程地质情况
根据铁道第三勘察设计院集团有限公司施工图所示,连续梁地处地震烈度为VIII度,动峰值加速度为0.2g。
5 确定安全措施
连续梁的专项安全施工方案里包括了以下多个环节的专项安全施工措施,具体包括以下几个:
承台基坑安全防护措施、
墩柱施工安全防护措施、 连续梁施工安全防护措施。 6 具体安全防护措施 6.1承台基坑安全防护措施 6.1.1机械设备安排表 (1)主要施工机械设备表 序号 1 2 3 4 5 6 7 设备名称 挖掘机 潜水泵 振动锤 自卸车 吊机 电焊机 发电机 规格型号 额定功率(kW) 生产能力 PC220 ≥150m3/h 60型 东风 55t履带吊 BX500 120 5.0 180 斗容≥1m3 15m3 数量 2台 6台 1台 4台 1台 3台 1台 (2)主要材料供应计划
桥墩38#(41#)单个承台主要材料需求量
序号 材料名称 1 2 3 4 槽 钢 工字钢 水 管 彩条布 规格型号 0.4m×6m I40,12m Φ50cm 单位 数量 备注 备用16片 备用12根 用于集中抽水 四周围护 片 147(148) 根 m m2 30 15 276(347) 桥墩39#(40#)单个承台主要材料需求量
序号 材料名称 1 槽 钢 规格型号 0.4m×6m 单位 数量 备注 备用16片 片 150(150) 2 3 4 工字钢 水 管 彩条布 I40,12m Φ50cm 根 m 30 15 备用12根 用于集中抽水 四周围护 m2 328(286) (3)劳动力组织计划表 序号 1 2 3 4 5 工种 打桩工 装吊工 吊车司机 电工 杂工 合计 人数 6 2 1 1 5 15 备注 含电焊工 6.1.2基坑开挖前的计算
由于跨石油管道连续梁的四个承台基坑所处地质条件都不利于直接放坡开挖,故根据现场实际情况,在39#、40#承台采用四周打槽钢进行防护,而在38#、41#承台采用两边槽钢防护两边放坡的方式进行防护。防护都采用40b型槽钢。
根据设计图纸及测量数据确定槽钢长度以及入土深度
墩 号 38 39 40 41 地面标高 承台底标高基坑深度(m) (m) (m) 69.021 68.901 68.864 69.760 64.318 63.022 63.255 64.870 4.703 5.879 5.609 4.890 地 质 情 况 回填土 砂 土 回填土 砂 土 回填土 砂 土 回填土 砂 土 选用长度 (m) 6 6 6 6 主墩39#、40#的底台尺寸为14.6×10.6m,按平面较承台每边宽1.0m的要求,则平面围护尺寸为16.6×12.6m。