目录
第一章 工程概况 ......................................................................................................................... 3
1.1 工程概况 ..............................................................................................................................................3 1. 2 合同项目和主要工程量 .....................................................................................................................3
第二章 施工总体部署和平面布置 ............................................................................................. 4
2.1施工总体部署 ........................................................................................................................................4
2.2施工平面布置 ........................................................................................................................................7
第三章 工程进度计划与措施 ..................................................................................................... 9
3.1 编制原则 .............................................................................................................................................9
3.2 工期目标 ...........................................................................................................................................10 3.3 施工进度计划 ...................................................................................................................................10 3.4 工程工期保证措施 ........................................................................................................................... 11
第四章 项目部及施工组织机构 ............................................................................................... 14
4.1 项目部组织机构 .................................................................................................................................14 4.2施工组织机构框图 ..............................................................................................................................15
第五章 施工方法及主要技术措施 ........................................................................................... 16
5.1 施工测量 .............................................................................................................................................16
5.2桥梁下部构造工程施工 ......................................................................................................................16 5.3桥梁的上部结构施工 ..........................................................................................................................23 5.4桥面系施工 ..........................................................................................................................................26 5.5通用工程项目施工 ..............................................................................................................................26 5.6桥头、台背回填施工 ..........................................................................................................................27
第六章 主要施工机具及劳动力使用计划 ............................................................................... 28
6.1劳动力使用计划 ..................................................................................................................................28
6.2施工机具使用计划 ..............................................................................................................................28
第七章 工程质量保证体系及措施 ........................................................................................... 29
7.1 质量方针、原则及目标 ...................................................................................................................29
7.2 工程质量的控制标准 .......................................................................................................................29 7.3 质量管理机构 ...................................................................................................................................29 7.4 工程质量控制点的设置 ...................................................................................................................37 7.5 质量管理措施和办法 .......................................................................................................................37 7.6 关键工序质量控制措施 ...................................................................................................................40
第八章 施工安全保证体系及措施 ........................................................................................... 42
8.1 安全目标 ...........................................................................................................................................42
8.2 施工安全管理组织机构 ...................................................................................................................43
1
8.3 安全保证体系 ...................................................................................................................................44 8.4 安全管理制度及办法 .......................................................................................................................46 8.5 施工现场安全措施 ...........................................................................................................................47
第九章 文明施工措施 ............................................................................................................... 49
9.1 文明施工的目标 ...............................................................................................................................49 9.2 文明施工的组织机构和实施方案 ...................................................................................................49 9.3 文明施工实施措施 ...........................................................................................................................50
第十章 环境保护保证措施 ....................................................................................................... 53
10.1 环境保护保证体系 .........................................................................................................................53
10.2 环境保护的目标 .............................................................................................................................53 10.3 环境保护措施 .................................................................................................................................53
第十一章 施工现场治安保卫防范措施 ................................................................................... 56 第十二章 成品保护和工程保修工作的管理措施和承诺 ...................................................... 57
12.1成品保护措施 ....................................................................................................................................57
12.2工程保修措施及承诺 ........................................................................................................................58
第十三章 紧急情况的处理措施 ................................................................................................. 59 第十四章 冬、雨季施工技术措施 ........................................................................................... 61
14.1冬季施工技术措施 ............................................................................................................................61
14.2 雨季施工措施 ...................................................................................................................................62
第十五章 与各协作单位的配合服务承诺 ............................................................................... 64
14.1与业主的配合服务承诺 ....................................................................................................................64
14.2与监理单位的配合服务承诺 ............................................................................................................64 14.3与政府部门的配合承诺 ....................................................................................................................65 14.4与协作单位的合作承诺 ....................................................................................................................66
2
第一章 工程概况
1.1 工程概况
1.1.1乐亭县水务局生产桥复建工程A包(周河湖林田庄生产桥)为生产生活用桥。
工程内容主要为基坑开挖、清淤外运、砼桩基础、浆砌石护坡、预制砼板、砼防撞护栏、桥面铺装、桥头搭板、钢筋制安等工程项目。
1.1.2工期目标
认真研究招标文件要求,现场施工条件及我公司预计将投入的施工实力和机械设备等,我公司将按招标文件的要求用74个日历天完成全部工程项目,即 年5月20开工, 年8月1日竣工。
1.1.3质量目标
达到招标文件要求的“合格”等级。 1.1.4安全生产目标
实现“工完”无重大安全事故:无因工死亡,无重伤事故,无重大火灾事故,无重大被盗事故,无重大设备事故和重大交通事故。
1.1.5 文明施工目标
加强工地管理,争创标化工地,争创文明施工工地。 1. 2 合同项目和主要工程量 1.2.1 土方工程
淤泥外运、土方开挖、土方回填及压实。 1.2.2 砌石工程
浆砌石护坡、砌体砂浆抹面、碎石垫层。