1.概述 ........................................................................................................................................................................ 2 2.适用范围 ................................................................................................................................................................ 2 3.网优集中化流程架构 ............................................................................................................................................. 2 4.各环节的流转规则 ................................................................................................................................................. 3 5.各环节的责任人及职责 ......................................................................................................................................... 5 6.各环节的具体工作内容 ......................................................................................................................................... 8 6.1全生命周期管理 ...................................................................................................................................................... 8 6.2需求管理(自上而下流程) ................................................................................................................................ 10 6.2.1省网优集中推送需求 ..................................................................................................................................... 10 6.2.2分公司确认并补充数据 ................................................................................................................................. 13 6.2.3省网优审核需求 ............................................................................................................................................. 13 6.3需求管理(自下而上流程) ................................................................................................................................ 14 6.3.1分公司上报需求 ............................................................................................................................................. 14 6.3.2省网优审核需求 ............................................................................................................................................. 15 6.4需求库优先级管理 ................................................................................................................................................ 16 6.5规划审核 ................................................................................................................................................................ 16 6.5.1设计单位录入规划数据 ................................................................................................................................. 16 6.5.2分公司工程部审核规划 ................................................................................................................................. 17 6.5.3分公司网优审核规划 ..................................................................................................................................... 18 6.5.4省公司网优审核规划 ..................................................................................................................................... 18 6.6铁塔对接审核流程 ................................................................................................................................................ 19 6.6.1分公司工程部导入铁塔确认单 ..................................................................................................................... 19 6.6.2分公司网优审核铁塔确认单 ......................................................................................................................... 20 6.6.3省网优审核铁塔确认单 ................................................................................................................................. 20 6.7勘察设计审核 ........................................................................................................................................................ 20 6.7.1设计单位启动勘察设计 ................................................................................................................................. 20 6.7.2分公司工程部审核勘察设计 ......................................................................................................................... 23 6.7.3分公司网优审核勘察设计 ............................................................................................................................. 24 6.7.4省网优审核勘察设计 ..................................................................................................................................... 25 6.8规划需求后评估 ................................................................................................................................................... 28 6.8.1省网优提取需求信息 ................................................................................................................................... 28 6.8.2省网优开展后评估 ....................................................................................................................................... 28 6.8.3省网优更新需求库 ....................................................................................................................................... 29 7.集中入网 ...............................................................................................................................................................29 7.1综资同步 ................................................................................................................................................................ 30 7.2开通申请 ................................................................................................................................................................ 30 7.2.1开通申请前的资料准备 ................................................................................................................................. 30 7.2.2开通申请的发起 ............................................................................................................................................. 31 7.3开通审核 ................................................................................................................................................................ 31
55
7.4传输调度 ................................................................................................................................................................ 33 7.5施工资料上传 ........................................................................................................................................................ 33 7.6工单审核 ................................................................................................................................................................ 33 7.6.1分公司初审 ..................................................................................................................................................... 34 7.6.2省公司二审 ..................................................................................................................................................... 34 7.7数据加载 ................................................................................................................................................................ 35 7.7.1无线网数据制作 ............................................................................................................................................. 35 7.7.2基站数据加载 ................................................................................................................................................. 36 7.8告警工参核查 ........................................................................................................................................................ 36 7.9单站网优验证 ........................................................................................................................................................ 37 7.10省公司单验审核 .................................................................................................................................................. 39 7.11入网后评估 .......................................................................................................................................................... 40 7.12资源核查更新 ...................................................................................................................................................... 40 7.13开通确认 .............................................................................................................................................................. 41 8.基站调整改造 .......................................................................................................................................................41 8.1LTE基站调整改造 ................................................................................................................................................... 41 8.2方案审核 ................................................................................................................................................................ 42 8.3无线数据制作 ........................................................................................................................................................ 42 8.4调整实施 ................................................................................................................................................................ 42 8.5网络测试 ................................................................................................................................................................ 42 8.6评估确认 ................................................................................................................................................................ 42 8.7流程归档 ................................................................................................................................................................ 43 9.LTE基站退网搬迁流程 ...........................................................................................................................................43 9.1 LTE基站退网类型说明 .......................................................................................................................................... 43 9.2 LTE基站退网流程 .................................................................................................................................................. 44 9.2.1临时停用 ......................................................................................................................................................... 44 9.2.2基站停用 ......................................................................................................................................................... 45 9.2.3基站搬迁 ......................................................................................................................................................... 49 10.其他要求事项 ......................................................................................................................................................50 10.1需求收集 .............................................................................................................................................................. 50 10.2日常规划与规划变更 .......................................................................................................................................... 50 10.3勘察设计变更 ...................................................................................................................................................... 50 10.4规划与勘察阶段总结 .......................................................................................................................................... 51 10.5工程优化前移阶段 .............................................................................................................................................. 51 10.5.1规划数据录入资管 ....................................................................................................................................... 51 10.5.2基站无线工参信息的现场采集 ................................................................................................................... 51 10.6工程验收 .............................................................................................................................................................. 52 11.评价指标 ..............................................................................................................................................................52 编制历史 ...................................................................................................................................................................55
55
1.概述
为指导各省开展好5G<E&NB集中规划设计审核及入网工作,特制定了《中国移动5G<E&NB集中规划设计审核及入网白皮书》,该流程规范对5G<E&NB集中规划设计审核及入网工作的相关工作流程作出了明确的规范要求。
2.适用范围
本流程规范适用于中国移动各省公司5G<E&NB无线网络站点从规划需求到开站入网各个环节的管控。
3.网优集中化流程架构
5G<E&NB无线网络新建站点集中规划设计审核及入网工作建议以“无线网规划设计审核电子平台”(以下简称“电子平台”)作为流程载体,完成新建站点从“需求管理、站址规划、勘察审核、设计审核到最终入网验收”所有流程的运转,且在电子平台中形成准确有效的5G<E&NB无线网络全流程管控数据。
5G<E&NB集中规划设计审核及入网流程如下图所示:
需求管理流程规划审核流程铁塔对接审核流程勘察设计审核流程集中入网流程规划需求后评估流程省网优集中推送需求分公司上报需求设计院录入规划数据分公司工程部导入铁塔确认单草案设计院启动勘察设计综资同步综资数据同步分公司工程部审核开通申请省网优提取需求信息开通审核分公司工程部审核分公司确认并补充数据省网优审核否(修改)变更分公司网优审核分公司网优审核否(修改)分公司网优审核数据加载省网优开展后评估省网优审核省公司网优审核需求库省公司网优审核变更告警验证省网优更新需求库非自建站点省公司网优审核单站验证需求库入网评估铁塔库规划库是否自建自建站点勘察设计库资源检查更新 55
4.各环节的流转规则
阶段名称 操作/触发条件 依据模板录入<测试黑点、弱覆盖投诉、2G高省网优集中推送需求 流量、高倒流、4G扩容、重要场景、MR以及NB、5G NR省公司负责部分的信息>“完整” 依据模板补充<测试黑点、弱覆盖投诉、2G高分公司确认并补充数据 流量、高倒流、4G扩容、重要场景、MR以及NB、5G NR地市公司负责部分的信息>“完整” <测试黑点、弱覆盖投诉、2G高流量、高倒流、省网优审核需求 4G扩容、重要场景、MR以及NB、5G NR需求审核>“合格” 依据模板录入<测试黑点、弱覆盖投诉、4G扩分公司上报需求 容、2G高流量信息、重要场景、MR以及NB、5G NR >“完整” <测试黑点、弱覆盖投诉、4G扩容、高倒流、省网优审核需求 MR需求审核、重要场景、MR以及NB 、5G NR >“合格” 基于需求方案并依据模板录入<规划方案信设计单位录入规划数据 息>“完整” 当前环节 流转环节 分公司确认并补充数据 省网优审核需求 设计单位录入规划数据 省网优审核需求 设计单位录入规划数据 需求管理 (自上而下流程) 需求管理 (自下而上流程) 分公司工程部审核规划 分公司网优审核分公司工程部审核规划 <站点位置和站点周边工程环境审核>“合格” 规划 <地市建设需求、网络结构审核及5G锚点审省公司网优审核分公司网优审核规划 核>“合格” 规划 规划审核 非自建站点流转至分公司工程部<整体规划方案解决测试黑点、弱覆盖投诉、导入铁塔确认2G高流量、5G审核、4G扩容等规划需求和需单,自建站点流求满足率>“达成”及<规划变更审核>“合格” 转至设计单位启动勘察设计 依据模板录入<铁塔确认单草案信息>“完整” <铁塔确认单草案信息>信息“合格” 分公司网优审核铁塔确认单 省网优审核铁塔确认单 设计单位启动勘察设计 分公司工程部审核勘察设计 分公司网优审核勘察设计 省公司网优审核勘察设计 分公司工程部启动综资同步 省网优开展后评估 省公司网优审核规划 铁塔对接审核流程 分公司工程部导入铁塔确认单 分公司网优审核铁塔确认单 省网优审核铁塔确认单 勘察设计审核 规划需求 后评估
<铁塔确认单草案信息>信息“合格”,审核确认后入库作为确认单 规划完成后依据模板录入<规划方案信息、图设计单位启动勘察设计 纸、照片>“完整” 分公司工程部审核勘察<规划方案信息、图纸、照片>“齐全”及<与设计 规划偏差>“合格” <与规划偏差>“合格”及<天面、站高、方向分公司网优审核勘察设角、下倾角、无线环境等工参数据的审核、物计 业点覆盖完整性、功率、天馈设置等室分覆盖方案、5G天馈方案>“合格” 省公司网优审核勘察设<全省及各地市的规划达成率>“合格”及<勘计 察设计变更审核>“合格” 开通确认后,从需求库中提取已建成站点的需省网优提取需求信息 求信息及覆盖目标区域 55