正文目录
1 编制说明 .......................................................................................................... 3 2 编制依据 .......................................................................................................... 4 3 施工具体部署 .................................................................................................. 5
3.1 材料准备 ........................................................................................................................ 5 3.2 现场准备 ........................................................................................................................ 5 3.3 施工流程 ........................................................................................................................ 5
4 平面布置 .......................................................................................................... 6
4.1 布置说明 ........................................................................................................................ 6 4.1.1 办公区...................................................................................................................... 6 4.1.2 管理人员及工人生活区.......................................................................................... 6 4.2 平面布置 ........................................................................................................................ 6 4.2.1 办公区...................................................................................................................... 6 4.2.2 管理人员及工人生活区.......................................................................................... 6
5 临建设施细部设计 ......................................................................................... 7
5.1 大门 ................................................................................................................................ 7 5.2 围墙 ................................................................................................................................ 7 5.3民工宿舍活动房 ............................................................................................................. 7 5.4 临建基础 ........................................................................................................................ 7 5.5 临时道路 ........................................................................................................................ 8 5.6 门卫室 ............................................................................................................................ 9 5.7 卫生间做法 .................................................................................................................... 9 5.8 浴室做法 ........................................................................................................................ 9 5.9 食堂做法 ........................................................................................................................ 9 5.10 水沟及沟盖板 .............................................................................................................. 9 5.11 排水系统 ...................................................................................................................... 9
6 注意事项 ........................................................................................................ 10 7 安全及环境保证措施 ................................................................................... 11
附图目录
附图一:《临建总平面布置图》……………………………………………………………13 附图二:《办公区各单位布置图》 ………………………………………………………14 附图三:《大门及门柱大样图》……………………………………………………………18 附图四:《旗台大样图》 …………………………………………………………………19 附图五:《围墙做法大样图》………………………………………………………………20 附图六:附图七:附图八:《工人浴室大样图》附图九:《锅炉房大样图》附图十:《排水沟大样图》
………………………………………………………21 ……………………………………………………22 ……………………………………………………23 ………………………………………………………………24 ………………………………………………………………25 《工人生活区厕所大样图》《工人生活区化粪池大样图》1 编制说明
2 编制依据
1)现场总平面布置图及建设单位指定的临时用地。 2)本工程施工组织设计及业主招标文件。
3)前期业主、监理、施工单位等商定的现场平面布置。
4)国家及地方现行的有关建筑工程管理、市政管理、环境保护等法规及规定。 5)、、、、、、、、、、。 6)现场的实际情况。
3 施工具体部署
3.1 材料准备
水泥为PO32.5的普通硅酸盐水泥、砖为MU5普通烧结砖及多孔砖、砂浆为M5水泥砂浆、涂料为白色乳胶漆涂料、磁片为300×200mm的白色磁片、活动板房屋面为压型彩钢板,材料进场时应有经相关单位确定认可的产品合格证书、产品性能检测报告,水泥要求复试,合格后方可用于施工,严禁使用国家明令淘汰的材料。其他材料、机具一并准备就绪。
根据临建初步规划进行活动房招标,确定活动房安装单位,并做好活动房材料及安装准备,待现场安装条件具备可以立即投入安装。 3.2 现场准备
、、、、、、、、、、、、、、、
,在临建施工前保证现场三通一平,场地周边围墙砌筑到位。部分区域找平后铺100mm厚C20混凝土硬化,基础施工完成并达到强度后开始活动板房安装。 3.3 施工流程
根据现场情况,本临建工程各分项流程大致施工步骤为:
场地平整 → 测量放线定位 → 活动房基础砌筑 → 活动房安装 → 绿化及CI
办公区及生活区临建施工方案(样板)