断路器安装作业指导书
编码:BDDQ-ZW-03
目 次
1 2 3 4 5 6 7
适用范围 ··················································································································· 27 编写依据 ··················································································································· 27 作业流程 ··················································································································· 27 安全风险辨析与预控 ···································································································· 28 作业准备 ··················································································································· 28 作业方法 ··················································································································· 29 质量控制措施及检验标准 ······························································································ 33
1 适用范围
本作业指导书适用于110~500kV电压等级,频率为50Hz的支柱式和罐式SF6断路器安装作业。 2 编写依据
表2-1 编 写 依 据
序号 1 2 3 4 5 6 7 8 引用资料名称 GBJ 147—1990《电气装置安装工程 高压电器施工及验收规范》 DL 408—1991《电业安全工作规程(发电厂和变电所电气部分)》 DL 5009.3—1997《电力建设安全工作规程(变电所部分)》 Q/CSG 10001—2004《变电站安健环设施标准》 Q/CSG 10007—2004《电力设备预防性试验规程》 《10kV~500kV输变电及配电工程质量验收与评定标准 第2部分:变电电气安装工程》 Q/CSG 11105.2—2008《南方电网工程施工工艺控制规范》 《中国南方电网公司十项重点反事故措施》 3 作业流程
作业(工序)流程见图3-1。
图3-1 作业(工序)流程图