1、基本概况 ................................................................................................................... 1 2、编制依据 ................................................................................................................... 1 3、工程概况 ................................................................................................................... 2 3.1 基本情况 ............................................................................................................... 2 3.2 地形地貌 ............................................................................................................... 2 3.3 工程地质 ............................................................................................................... 2 3.4工程地质条件 ........................................................................................................ 3 3.5地下水情况 ............................................................................................................ 4 3.6周围建筑物 ............................................................................................................ 4 4、基坑护壁及排水设计方案 ......................................................................................... 4 4.1喷锚支护设计 ........................................................................................................ 5 4.2排水设计 ............................................................................................................... 7 5、施工准备 ................................................................................................................... 7 5.1 劳动力计划 ........................................................................................................... 7 5.2 主要进场仪器设备计划 ........................................................................................ 8 5.3 现场总平面布置原则 ............................................................................................ 8 6、总体进度计划 ............................................................................................................ 9 7、土方施工 ................................................................................................................. 10 7.1 开挖顺序及坡道留设 .......................................................................................... 10 7.2 渣土消纳 ............................................................................................................. 10 7.3挖土及运输车辆的配置 ....................................................................................... 10 7.4施工方法 ............................................................................................................. 10 7.5验槽 ..................................................................................................................... 11 8、本基坑工程难点和重点 ........................................................................................... 11 8.1工期紧 ................................................................................................................. 11 8.2插入工序多 .......................................................................................................... 12 8.3坑中坑开挖高差大 ............................................................................................... 12 8.4天气影响 ............................................................................................................. 12 9、基坑监测方案及紧急情况预案 ................................................................................ 12 9.1基坑监测 ............................................................................................................. 12 9.2 紧急预案 ............................................................................................................. 13 9.3雨季施工措施 ...................................................................................................... 14 10、文明施工与环境保护 ............................................................................................. 14 10.1噪声控制 ............................................................................................................ 14 10.2粉尘 ................................................................................................................... 14 10.3 遗撒控制 ........................................................................................................... 15 10.4 安全措施 ........................................................................................................... 15
计 算 书 ....................................................................................................................... 17 1、参数信息 .............................................................................................................. 17 2、土钉(含锚杆)抗拉承载力的计算 .......................................................................... 18 3、土钉墙整体稳定性的计算 .................................................................................... 20 4、抗滑动及抗倾覆稳定性验算 ................................................................................ 26
0
……………………………………………………………精品资料推荐…………………………………………………
1#、2#楼深基坑土方开挖及支护工程施工方案
1、基本概况
项 目 工程名称 工程地点 建筑面积 建筑高度 结构形式 结构层次 建设单位 设计单位 监理单位 勘察单位 内 容 承德凤凰御都小区1#、2#楼 河北承德市开发区 1#楼:11682.66㎡ 2#楼:12268.39㎡ 80.45m 抗震墙 地下2层地上27层 承德凤凰山房地产开发有限公司 北京京澳凯芬斯设计有限公司 承德城建工程项目管理有限公司 承德水文地质工程地质勘察院 基坑支护设计 北京京澳凯芬斯设计有限公司 施工单位
中天建设集团有限公司 2、编制依据
⑴ 总平面布置图 ⑵《岩土工程勘察报告》 ⑶ 设计施工图纸
⑷《建筑基坑支护技术规程》(JGJ120-99)
⑸《锚杆喷射混凝土支护技术规范》(GB50086-2001) ⑹《工程测量规范》(GB50026-2008)
1
……………………………………………………………精品资料推荐…………………………………………………
⑺《钢筋焊接及验收规程》(JGJ18-2003) ⑻《基坑土钉支护技术规程》(CECS 96:97) ⑼《建筑施工安全检查标准》(JGJ59-99)
⑽《建筑工程施工质量验收统一标准》(GBJ50300-2001)
3、工程概况
3.1 基本情况
1-2#楼工程位于承德凤凰御都住宅小区,主楼地下二层,地上二十七层,结构形式为抗震墙结构。地下二层为地下室,地上一、二层为商业网点及其它用房,地上三~二十七层为住房。1#楼总建筑总面积11682.66m2,2#楼总建筑面积12268.39 m2,主楼基底建筑面积353.38 m2。
1#楼±0.000为311.60m,基础垫层底标高为-9.15m,对应标高302.45m;集水坑垫层底绝对标高为300.10m。
2#楼±0.000为312.00m,基础垫层底标高为-9.15m,对应绝对标高302.85m;集水坑垫层底绝对标高为300.50m。 3.2 地形地貌
场区地貌单元属承德市滦河二级阶地,场地整平标高为309.37~310.54m,较为平整。 3.3 工程地质
根据钻探和原位测试及土工试验结果,在勘察深度范围内,按地基岩土的物质组成、结构构造、物理力学性质及成因类型等特点,场区地层自上而下划分为五个工程地质层,依次为:杂填土、粉土、细砂、圆砾、砾石,现分层如下:
⑴ 第一层:杂填土,杂色,稍蜜,稍湿,成份主要以碎石、碎砖、粉土为主。本层全区分布,厚度为0.90~2.40m,平均厚度为1.63m,层底埋深0.90~2.40m,平均埋深为1.63m,底层标高为307.55~309.02m。
⑵ 第二层:粉土,褐黄色,稍密,稍湿,摇震反应迅速,无光泽反应,韧性低,干强度低,局部相变为粉砂。本层全区分布,厚度为2.90~5.50m,平均
2
……………………………………………………………精品资料推荐…………………………………………………
厚度为4.13m,层底埋深4.20~7.10m,平均埋深为5.76m,层底标高为303.13~305.34m。
⑶ 第三层:细砂,褐黄色,稍湿,成份主要以石英、长石为主。本层在大部分钻孔有所分布,厚度为0.40~2.10m,平均厚度为1.36m,层底埋深6.50~7.80m,平均埋深为7.40m,层底标高为302.04~302.87m。
⑷ 第四层:圆砾,褐黄色,中密,水位以上稍湿,水位以下饱和,砾石成份以火成岩、燧石为主,砾石成亚圆状,粒径大于2mm的颗粒含量大于总重量的50﹪,中粗砂充填,分选性差。本层全区分布,揭露厚度为3.20~11.80m,平均揭露厚度为7.74m,揭露底深11.00~16.50m,平均揭露底深为14.61m,揭露底层标高为293.35~298.95m。
⑸ 第五层:砾岩,本层为中生界侏罗系中统后城组砾岩,俗称“承德砾岩”。本层又分为强风化砾石和中风化砾石。
强风化砾石:紫褐色,粒状结构,块状构造,硅质胶结,裂隙较发育,本层岩石属较软岩,岩体完整程度为破碎,岩体基本质量等级为Ⅳ级。本层全区分布,但只有部分钻孔揭露,揭露厚度为1.20~1.50m,平均揭露厚度为1.34 m,层底埋深17.00~18.00m,平均埋深为17.38m,层底标高为292.05~293.04m。
中风化砾石:紫褐色,粒状结构,块状构造,硅质胶结,本层岩石属较硬岩,岩体完整程度为较完整,岩体基本质量等级为Ⅲ级。本层全区分布,但只有部分钻孔揭露,最大揭露厚度为7.80m,最大揭露深度为25.00m。 3.4工程地质条件
根据岩土工程勘察报告,现将拟建场区地质参数汇总于下表1: 表1 拟建场区地质参数汇总表 土层 1 2 3 4 5 6 土性 杂填土 粉土 细砂 圆砾 强风化砾岩 中风化砾岩 层底标高(m) 307.55-309.02 303.13-305.34 302.04-302.87 293.35-298.95 292.05-293.04 平均层厚(m) 1.63 4.13 1.36 7.74 1.34 各层的分布及物理力学性质指标详见“工程地质剖面图”和“地层岩性及土
3
……………………………………………………………精品资料推荐…………………………………………………
的物理力学性质综合统计表”。
根据勘察单位的勘察报告,该工程地层分布情况概述如下表2: 表2 典型地层剖面 序号 1 2 3 4 3.5地下水情况
根据地质勘察报告,场区内均见地下水,属第四系潜水,圆砾层为其含水层,稳定水位埋深为8.50~9.70m,稳定水位标高为300.54~300.84m。地下常水位在设计基底标高以下,所以暂不必考虑基坑降水施工。 3.6周围建筑物
1#楼东面距3#楼13m(3#楼为在建住宅楼工程,主体已封顶,地上5层,无地下室),2#楼距5#楼16m(5#楼为在建住宅楼工程,主体已封顶,地上5层,无地下室),2#楼南面距农科所家属楼30.8m,2#楼东南距7#楼13.2m,西面距马路边18.8m, 1#楼北面距职业学院宿舍41.68m。
成因年代 Q4ml Q4al+pl Q4al+pl Q4al+pl 岩土层名称 杂填土 粉土 细砂 圆砾 0.4~2.1 3.2~11.8 柱状图 层 厚 (m) 0.90~2.40 简 述 由碎石、碎砖和粉土组成; 局部相变为粉砂 由长石,石英 为主组成, 火成岩、燧石为主 2.90~5.55 4、基坑护壁及排水设计方案
根据现场实际情况基坑距围墙及建筑物距离太近,采用喷锚支护。 4.1喷锚支护设计
4.1.1 设计依据
(1)甲方提供的地下室平面图
(2)《锚杆喷射混凝土支护技术规范》(GB50086-2001)
4