国电克拉玛依热电联产 2×350MW机组工程 编号 作 业 指 导 书 编制 年 月 日 审核 年 月 日 年 月 日 年 月 日 批准 年 月 日 修改内容 1 2 3 4
目录
1.编制依
XX公司 #1锅炉水压试验 国电克拉玛依项目部 共 33 页 修改人 审核、批准 据··························································1
2.概
述······························································1
3.主要工程
量························································3
4.作业条
件··························································3
5.作业方
案··························································6
6.QA检查
单························································14
7.安全与文明施工及环境管
理··········································14
8.强制性条文执行计
划················································21
9.反馈
单····························································25
10.附
件·····························································27
1.编制依据
1.1《工程建设标准强制性条文》(电力工程部分)(2006年版)
1.2《电力建设施工技术规范》第2部分:锅炉机组(DL/T 5190.2—2012)
1.3《电力建设施工质量验收及评价规程》第2部分:锅炉机组(DL/T 5210.2-2009)
1.4《火力发电厂焊接技术规程》DL/T869-2012
1.5《电力建设施工质量验收及评价规程》第7部分:焊接(DL/T 5210.7-2009)
1.6《电力建设施工技术规范》第五部分:管道及系统(DL5031.5-2012)
1.7 《电力建设施工质量验收及评价规程》第5部分:管道及系统(DL/T 5210.5-2009)
1.8《火力发电厂水汽化学监督导则》DL/T561-95
1.9《电站锅炉压力容器检验规程》(DL647-2004)
1.10《电力建设安全工作规程》(火力发电厂部分)(DL5009.1-2002)
1.11《国家电网公司基建安全管理规定》2010版
350MW超临界锅炉水压试验作业指导书