某斜拉桥悬拼法施工工艺

天下 分享 时间: 加入收藏 我要投稿 点赞

某跨海大桥(引桥)

预应力连续梁悬拼法施工工艺

(修改稿)

二○○三年8月

目录

1、编制说明 .................................................................................................................. 3 1.1 工程概况 .................................................................................................................... 3 1.2 气候条件 .................................................................................................................... 3 1.3编制依据 ..................................................................................................................... 4 2、施工准备 .................................................................................................................. 4 2.1 场地布置 .................................................................................................................... 4 2.2 主要机具设备 ........................................................................................................... 4 2.3材料组织 ..................................................................................................................... 5 2.4 劳动力组织 ................................................................................................................ 6 2.5 进度计划 .................................................................................................................... 6 3、节段悬拼 .................................................................................................................. 6 3.1概述 .............................................................................................................................. 6 3.2节段悬拼流程 ............................................................................................................ 7 3.3节段悬拼质量标准 ................................................................................................... 8 3.4节段预制及存放 ....................................................................................................... 8 3.5 胶拼面处理 ................................................................................................................ 8 3.6 节段整修 .................................................................................................................... 9 3.6 悬拼吊架 .................................................................................................................... 9 3.7节段起吊与运输 .....................................................................................................10 3.8 湿接缝施工 ..............................................................................................................10

3.9 节段的胶拼 ..............................................................................................................11

3.9.1 节段胶拼工艺流程 ........................................................................................11 3.9.2 节段胶拼准备工作 ........................................................................................12 3.9.3 节段胶拼 ...........................................................................................................12 3.10 预应力筋的张拉及压浆 .....................................................................................14 3.11 悬拼线形控制 .......................................................................................................15 3.12 合龙段施工 ...........................................................................................................16 3.13缺陷及预留孔的修补 ..........................................................................................17 4.质量控制及安全措施 ........................................................................................... 17 4.1 质量控制 ..................................................................................................................17 4.2 安全注意事项和环境控制 ..................................................................................18

1、编制说明

本施工组织设计是某桥工程项目总体施工组织设计的补充,是某桥上部结构梁体节段悬臂拼装的实施性施工组织设计。

1.1 工程概况

某桥为 至 的第三条连接线,全线总长2119.712m,桥长1825m,桥式布置(从北向南)为(5×60)+(2×60)+(110+180+110)+(9×60)+(7×60+45)m,共五联,主桥为110+180+110m预应力混凝土斜拉桥,除南引桥S16~S17号墩跨为45m跨外,引桥其余跨均为60m的预应力砼等高连续箱梁,北引桥1~N2为2×60m异形段箱梁,连接A、B匝道。匝道A为(4×22.6)+(4×22.6)+(4×22.6)=271.2m连续等高箱梁;匝道B为(3×22.6)+(3×22.6)+(3×22.6)+(26.6+37+22.6)+(3×22.6)+(3×22.6)=519.6m混凝土箱梁。

采用悬拼法施工的梁段从主桥1#墩至S14#墩,共34跨,28个“T”构,它们是主桥2、3号墩“T”构和引桥S1、S2、S3、S4、S5、S6、S7、S8、S10、S11、S12、S13号墩“T”构。主桥每个“T”构的拼装块件数为48块,即每个悬臂端24块;引桥每个“T”构的拼装块件数为12块,即每个悬臂端6块。

全桥共悬拼480个块段,其中1#—4#墩为向下的圆曲线,4#—S4#墩为5%的下坡,S4#—S6#墩为向上的圆曲线,S6#—S14#墩为平坡。预制梁块长有2m、3m、4m三种,梁体宽度主桥为15.90m,引桥为12.95m。各种块件的数量如下: 块 段 数 量 主桥 引桥 1.2 气候条件

某地位于北回归线以南,地处低纬,又位于海岸地区,深受海洋和季风影响。某地的气候具有湿暖、多雨、湿热和干湿季明显等特点,属热带季风气候。全年主要分冬夏两季,春秋短暂而不明显。夏热多雨,冬稍干冷,春湿多雾,秋日晴

0#块(现浇) 4 24 2 m 48 —— 3m 8 —— 4m 136 288 合龙段 6 28 直线段 4 8

朗。

某地的年平均气温为22.3℃,气温的年较低为14℃,变化比较平缓。其中一月最冷,平均气温为14.6℃,但最低气温仍在5℃以上,最冷的纪录是-1.8℃。七月份则最为炎热,平均气温达28.5℃左右,最热的纪录是38.9℃。某地年降雨量充沛,平均为2030毫米,四月至十月为雨季,而五月份降雨量最多。 平均来说,每年在某地一百海里范围内经过的热带风暴为2.1次,其中1.2次是台风。每年在一百海里范围内经过的风暴最多为6次,风暴常发生于五月至十二月,其中约85%集中于七月至十月。

1.3编制依据

(1)招标文件及补遗书;

(2)设计/施工投标初步设计(主方案)设计说明; (3)设计/施工投标中标通知; (4)上部结构设计图纸;

(5)《钢筋混凝土及预应力混凝土结构规章》 (6)《屋宇结构及桥梁结构之安全及荷载规章》 (7)施工组织设计

2、施工准备

2.1 场地布置

祥见《珠海岸生产区场地布置图》,箱梁块件的预制、存放、起运上船及悬拼吊架的组拼均在珠海岸生产区完成。珠海案生产区距离桥址约4公里。

2.2 主要机具设备

桥梁节段悬拼工作主要包括:节段修整、起吊、运输;节段胶拼;预应力张拉/压浆;合龙段混凝土灌注等。完成上述工作的主要机具设备如下: 序号

名称及规格 单位 数量 备注