目录

第一章 编制依据及原则 ............................................... 1

1.1编制依据 ............................................................................................................................... 1

1.2编制原则 ............................................................................................................................... 1 1.3 编制范围 ............................................................................................................................... 1

第二章 工程概况 ..................................................... 2

2.1工程简介 .............................................................................................................................. 2

2.2周边环境 .............................................................................................................................. 2 2.3结构设计及施工方法 .......................................................................................................... 2 2.4支护参数 .............................................................................................................................. 2 2.5工程地质及水文概况 .......................................................................................................... 3

2.5.1工程地质 ........................................................... 3 2.5.2水文情况 ........................................................... 4 2.6工程重难点分析 .................................................................................................................. 5

第三章 施工总体部署 ................................................. 1

3.1施工目标 .............................................................................................................................. 1

3.1.1质量目标 ........................................................... 1 3.1.2安全生产目标 ....................................................... 1 3.1.3工期及环保文明施工目标 .............................................. 1 3.2施工组织 .............................................................................................................................. 1

3.2.1劳动力安排 ......................................................... 1 3.2.2机械设备配置 ....................................................... 2 3.3管理组织机 .......................................................................................................................... 3 3.4施工进度安排 ...................................................................................................................... 4

第四章 风、水、电布设方案 ........................................... 1

4.1洞内管、路、线总体布置 .................................................................................................. 1

第五章 斜井开挖及支护施工方案 ....................................... 1

5.1斜井施工方案 ...................................................................................................................... 1

5.1.1斜井明挖段施工 ..................................................... 1 5.1.2斜井暗挖段施工 ..................................................... 3 5.1.3斜井明暗挖交接处施工 ............................................... 4 5.2斜井与主体连接处的施工 .................................................................................................. 4 5.3二次衬砌施工方案 .............................................................................................................. 4

第六章 主要分项工程施工工艺 ......................................... 1

6.1基坑围护桩施工 .................................................................................................................. 1

6.1.1施工工艺 ........................................................... 1 6.1.2施工准备 ........................................................... 1 6.1.3测量放线 ........................................................... 1 6.1.4埋设护筒 ........................................................... 1

6.1.5泥浆制备 ........................................................... 2 6.1.6钻进成孔 ........................................................... 2 6.1.7清孔 ............................................................... 2

6.2混凝土施工 .......................................................................................................................... 3 6.2.1施工工艺 ........................................................... 3 6.2.2喷射前准备工 ....................................................... 3 6.2.3施工方法 ........................................................... 4 6.3锚杆 ...................................................................................................................................... 5

6.3.1砂浆锚杆施工工艺流程 ............................................... 5 6.3.2施工准备 ........................................................... 5 6.3.3测量放线 ........................................................... 5 6.3.4造孔 ............................................................... 5 6.3.5注浆、插锚杆 ....................................................... 6 6.3.6锚杆施工要点 ....................................................... 6 6.3.7砂浆锚杆检查验收 ................................................... 6 6.4超前小导管注浆施工工艺 .................................................................................................. 7 6.5回填注浆 .............................................................................................................................. 9 6.6台阶法施工 ........................................................................................................................ 10 6.7钢筋网施工 ........................................................................................................................ 10 6.8管棚钻机施作大管棚 ........................................................................................................ 11 6.9降水措施 ............................................................................................................................ 14 6.10斜井防淹措施 .................................................................................................................. 15

第七章 斜井钻爆设计 ................................................. 1

7.1主要对策 .............................................................................................................................. 1

7.2斜井开挖及钻爆 .................................................................................................................. 3

7.2.1 斜井爆破要求 ....................................................... 3 7.2.2斜井爆破方法 ....................................................... 4 7.3斜井爆破安全防护 .............................................................................................................. 8 7.3.1爆破防护措施 ........................................................... 8 7.3.2安全警戒措施 ........................................................... 9

7.3.2.1警戒布置 ............................................... 9 7.3.2.2警戒过程 ............................................... 9 7.3.2.3联络方式 .............................................. 10

第八章 斜井监控方案 ................................................. 1

8.1施工测量的组织 .................................................................................................................. 1 8.2施工测量、监控量测主要仪器设备 .................................................................................. 1 8.3施工监测的技术要求 .......................................................................................................... 2 8.4施工监测的方法 .................................................................................................................. 3

第一章 编制依据及原则

1.1编制依据

1.1.1.大连地铁一期工程设计总承包合同;

1.1.2业主关于西安路站增加临时施工斜井的工作联系单; 1.1.3《大连市地铁1、2号线工程施工图纸设计文件组成与内容》; 1.1.4国家现行的相关规范、规程及标准,辽宁省大连市关于市政工程施工的相关要求,国家及地方政府关于环境保护、职业健康等方面的法规;

1.1.5我公司在城市轨道交通方面的施工经验,及现有的施工技术、管理、机械设备配套能力和资金投入能力等;

1.2编制原则

1.2.1严格执行国家及大连市政府所制订的法律、法规和各项管理条例,并做到模范守法,文明施工;

1.2.2针对城市中心区施工的特点,科学安排 、合理组织、严格管理、精心施工,以减少对周围环境及居民正常生活的影响;

1.2.3以成熟的施工技术及先进的设备和施工工艺,确保施工安全和工程质量,按期为业主提供一个优质的工程产品;。

1.2.4以切实有效的技术措施和先进工艺,防止坍塌,控制地面沉陷,确保建(构)筑物及地下管线等不受损坏,维持正常使用功能,做到不断、不裂、不漏、不渗;

1.2.5在施工组织设计的基础上,根据现场的实际施工条件,优化施工安排,均衡生产,保证工期;

1.3 编制范围

编制范围:大连地铁1号线103标段工程西安路站临时斜井明挖段、暗挖段开挖、支护施工。

第二章 工程概况

2.1工程简介

临时施工斜井位于车站中部永平街南侧,施工围挡占用部分人行道和永平街半副路面。斜井净宽4.5m,全长156m,其中明挖段长80.98m,暗挖段75.05m,斜井以14%纵坡下落至主体结构拱脚下,车站主体范围斜井为平直段。

2.2周边环境

施工斜井北侧为西安路公寓:22层高层及24层高层,南侧为四十八中4层教学楼,斜井开挖边缘距离公寓18层高层的1层裙房水平距离22m左右,距离22层高层及24层高层水平距离15m左右,距离四十八中4层教学楼水平距离12m左右。

2.3结构设计及施工方法

斜井明挖段结构净空考虑尺寸考虑了车道宽、管线要求和安全距离要求确定,设计采用U形槽断面,明挖基坑深度小于4m的采用放坡度喷锚支护,坡度1:0.2,剖面采用150厚C25喷射混凝土,φ6.5,150×150mm,根据基坑深度采用3~4排φ22砂浆锚杆。基坑深度大于4m采用孔桩支护。

斜井暗挖结构净空考虑尺寸考虑了车道宽、管线要求和安全距离要求确定,同时满足施工车站主体结构需要。暗挖通道断面结构形式主要为三心圆拱直墙断面结构,内部净空宽×高为4.5×5.66~10.1m,结构型式为初期支护和复合式衬砌。

临时斜井负责车站主体部分施工,斜井先施工明挖基坑段,基坑开挖至明暗挖分界通道拱顶处,施工暗挖通道的超前直护,明暗挖分界处应预留一定的岩柱,待基坑开挖完成后进行暗挖通道的施工,暗挖通道采用台阶法施工。

2.4支护参数

2.1-1明挖段支护参数标 项 目 桩间锚杆 围护支护 钢筋网 喷射混凝土 钻孔桩 支撑 钢筋混凝土支撑 材料及规格 结构尺寸 φ22砂浆锚杆,L=2.5m 1.5×2.0m φ6.5,150×150mm C25网喷混凝土 C30混凝土 600×800mm 基坑壁布设 0.10mm φ1000,间距2m 间距4.0~5.0m 2.1-2暗挖段支护参数标 项 目 材料及规格 结构尺寸 纵间距:两品钢支撑;环间离:0.4m 间距1m×1.0(1.5)m,浆液水泥浆 拱墙单层钢筋网 0.25(0.3)mm φ1000,间距2m 间距0.75 m 间距0.75 m 0.25mm 初期 支护 钢筋网 喷射混凝土 钻孔桩 格栅钢支撑 临时 钢支撑 支护 喷射混凝土 临时 拱、墙 衬砌 底板 超前小导管及注浆 φ32×3.25,L=2.5m (进洞断面设) 砂浆锚杆 φ22,L=3.0m φ8,150×150mm C25网喷混凝土 C30混凝土 φ22、φ14、φ6 I22a C25网喷混凝土 C40防水钢筋混凝土,P10 0.3m C40防水钢筋混凝土,P10 0.3m 2.5工程地质及水文概况

2.5.1工程地质

1、地形地貌及既有建筑物和管线

拟建大连地铁1#、2#线西安路站地貌为马栏河二级阶地,后经人工改造,场地地形较平坦,地面高程9.22~12.24m,现为街道及商业区,周边建筑物密集,管线、管道众多。

2、场地地质构造

勘察为发现明显的断裂构造,局部受区域构造影响,岩石节理裂隙较发育,场地构造稳定性总体较好。

3、场地底层概述

车站范围内上覆第四系人工堆积层(Q4ml),第四系上更新统冲洪积层(Q3dl+pl),下覆震旦系长岭子组钙质板岩(Zwhc),中生代燕山辉绿岩(βμ),各地层分述描述如下:

1)第四系全新统人工堆积层(Q4ml)

①1素填土:褐色-黑灰色,主要成份为粘性土,碎石,建筑垃圾等杂志组成。碎石粒径20-120mm不等,局部块石,硬杂质含量占全质量30~70%左右。稍湿-饱和,松散-稍密状态,该层局部分布,层厚1.00~5.80m,层底高程5.2~11.3m。

2) 第四系上更新统冲洪积层(Q3dl+pl)

斜井专项施工方案 - 图文

目录第一章编制依据及原则...............................................11.1编制依据.......................................................................................................