斯里兰卡阿塔纳水厂
Gampaha,Attanagalla&Minuwangoda Integrated Water Supply Scheme
雨季施工专项施工方案
Method Statement in Rainy Season
编制: Prepared By: 审核: Reviewed By: 批准: Approved By:
CMEC公司斯里兰卡阿塔纳水厂项目部
Gampaha,Attanagalla & Minuwangoda Integrated Water Supply Scheme
编制时间:2017年09月01日 Preparation Date:1st September , 2017
目 录
Contents
第一节、编制依据 ................................................ 01 Chapter I Preparation Basis
第二节、工程概况 ................................................ 01 Chapter II Project Overview
第三节、 雨季施工原则 ........................................... 04 Chapter III Construction Principles in Rainy Season
第四节、施工步骤 ................................................ 05 Chapter IV Construction Procedures
第五节、雨季施工管理目标 ........................................ 10 Chapter V Construction Management Targets in Rainy Season
第六节、 雨季施工的主要部位 ..................................... 11 Chapter VI Major Areas for Construction in Rainy Season
第七节、雨季施工主要技术管理措施 ................................. 11 Chapter VII Main Technical Measures
7.1 雨季施工管理 ............................................ 11 7.1 Construction Management in Rainy Season
7.2 地基与基础工程 ........................................ 13 7.2 Foundation and Base Works
7.3 地下防水工程 ........................................... 16 7.3 Underground Waterproof Engineering
7.4钢筋工程 ............................................... 17 7.4 Reinforcement Works
7.5模板工程 ............................................... 18 7.5 Formwork
7.6 混凝土工程 .............................................. 19 7.6 Concrete Works
7.7 机电安装工程 ............................................ 22
7.7 Mechanical and Electrical Installation Works
7.8 砌筑工程 ................................................ 30 7.8 Masonry Works
7.9装饰装修工程 .......................................... 31 7.9 Decoration Engineering
7.10脚手架工程 .............................................. 33 7.10 Scaffolding Works
7.11物资及设备的堆放 ........................................ 35 7.11 Storage for Materials and Equipment
7.12现场临电工程 ............................................ 38 7.12 Site Temporary Power Work
7.13现场排水 ................................................ 39 7.13 Site Drainage Works
第八节、雨季安全技术措施 ........................................ 43
Chapter VIII Safety Measures for Construction in Rainy Season
8.1机械安全技术措施 ......................................... 43 8.1 Safety Measures for Equipment Operations
8.2施工安全技术措施 ...................................... 44 8.2 Construction Technical Safety Measures
8.3消防管理措施 .......................................... 48 8.3 Fire Fighting Controlling Measures
8.4环境保护措施 ............................................. 48 8.4 Environmental Protection Measures
8.5 人员安全技术保障 ........................................ 49 8.5 Technical and Safety Guarantee for Construction Personnel
8.6雨季卫生防疫安全隐患及预防措施 ........................... 50 8.6 Disease Prevention Measures and Health Protection
8.7雨季安全施工工作检查 ..................................... 52 8.7 Safety Construction Supervising and Inspection
第九节、 附件 ............................................... 53
Chapter IX Appendix
第一节、 编制依据 Chapter I Preparation Basis
序号 S/N 1 文件名称 Documentation lists 《建筑工程施工现场供电安全规范》 Code for Safety of Power Supply and GB50194-2014 Consumption for Construction Site 《建筑工程施工质量验收统一标准》 2 Unified Standard for Construction Quality Acceptance of Building Engineering 《建筑机械使用安全技术规程》 3 Technical Specification for Safety Operation of Construction Machinery 《施工现场临时用电安全技术规范》 4 Technical Code for Safety of Temporary Electrification on Construction Site 《建筑施工安全检查标准》 5 Standard for Construction Safety Inspection 《职业健康安全管理手册》 6 Occupational Health and Safety Management System Manual 7
第二节、工程概况 Chapter II Project Overview
第 0 页 共 63页
文件编号 File No. 备注 Remarks GB50300-2013 JGJ33-2011 JGJ46-2012 JGJ95-2011 公司颁发的《安全施工手册》 Construction Safety Manual by CMEC